Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

EMBASSY RIVERINE

by SUMMIT DEVELOPMENTS LIMITED · 217 homes · 50.81 acres · 25 towers · Bengaluru North

Upcoming Under construction, due Sep 2032. 2% built with 2% of the time used. 34% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
2% built

Due 30 Sep 2032. 2% of the time from RERA approval to the deadline has passed.

Built2%
Time used2%
How much is sold?143 left
34% booked

74 of 217 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
4 homes per acre

Similar projects within 3 km: 9 per acre. 75% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?4 due so far
50% on time

Of its 9 RERA projects in Bengaluru Urban: 2 delivered on time, 2 late (after the date first promised), 5 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Sep 2026
  2. Approved by RERA9 Sep 2026
  3. Today24 Oct 2026

    2% of the time to the deadline has passed.

  4. If it slips like a typical project2 Jul 2033

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q2 2026-272%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Cluster 10%
Cluster 20%
Cluster 30%
Cluster 40%
Cluster 50%
Cluster 60%
Cluster 70%
Cluster 80%
Cluster 90%
Cluster 100%
Cluster 110%
Cluster 120%
Cluster 130%
Cluster 140%
Cluster 150%
Cluster 160%
Cluster 170%
Cluster 180%
Cluster 190%
Cluster 200%
Cluster 210%
Cluster 220%
Cluster 230%
Cluster 240%
Cluster 250%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

74 booked143 leftQ2 2026-27

Still available: 27 × 4 BHK, 85 × 4.5 BHK, 31 × 5 BHK.

Booked, by type

4 BHK21 of 48
4.5 BHK52 of 137
5 BHK1 of 32

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

4.5 BHK
3,626 sq ft
337 m² carpet · sizes 3,569–3,655 sq ft (34 at this size)
799 m² land share · 48 m² balcony/terrace · 3 parking spaces
137 homes · 63% of the project
4 BHK
2,828 sq ft
263 m² carpet · sizes 2,786–2,843 sq ft (25 at this size)
646 m² land share · 47 m² balcony/terrace · 2 parking spaces
48 homes · 22% of the project
5 BHK
4,584 sq ft
426 m² carpet · sizes 4,584–4,620 sq ft (30 at this size)
1,066 m² land share · 80 m² balcony/terrace · 4 parking spaces
32 homes · 15% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Cluster 12 floors
Cluster 22 floors
Cluster 32 floors
Cluster 42 floors
Cluster 52 floors
Cluster 62 floors
Cluster 72 floors
Cluster 82 floors
Cluster 92 floors
Cluster 102 floors
Cluster 112 floors
Cluster 122 floors
Cluster 132 floors
Cluster 142 floors
Cluster 152 floors
Cluster 162 floors
Cluster 172 floors
Cluster 182 floors
Cluster 192 floors
Cluster 202 floors
Cluster 212 floors
Cluster 222 floors
Cluster 232 floors
Cluster 242 floors
Cluster 252 floors

Cluster 1: 14 homes, 15 m tall · Cluster 2: 9 homes, 15 m tall · Cluster 3: 5 homes, 15 m tall · Cluster 4: 8 homes, 15 m tall · Cluster 5: 10 homes, 15 m tall · Cluster 6: 12 homes, 15 m tall · Cluster 7: 10 homes, 15 m tall · Cluster 8: 8 homes, 15 m tall · Cluster 9: 11 homes, 15 m tall · Cluster 10: 8 homes, 15 m tall · Cluster 11: 10 homes, 15 m tall · Cluster 12: 12 homes, 15 m tall · Cluster 13: 10 homes, 15 m tall · Cluster 14: 8 homes, 15 m tall · Cluster 15: 5 homes, 15 m tall · Cluster 16: 9 homes, 15 m tall · Cluster 17: 14 homes, 15 m tall · Cluster 18: 5 homes, 15 m tall · Cluster 19: 6 homes, 15 m tall · Cluster 20: 7 homes, 15 m tall · Cluster 21: 4 homes, 15 m tall · Cluster 22: 4 homes, 15 m tall · Cluster 23: 12 homes, 15 m tall · Cluster 24: 14 homes, 15 m tall · Cluster 25: 2 homes, 15 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project4
Typical within 3 km (8)9
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project75%
Typical within 3 km (8)58%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
50.81 acres

2,05,610 m²

Ground covered by buildings
25% of the land

51,205 m²

Floor-area ratio
0.47

Floors built per unit of land: 0.47 m² of floors for each m² of land.

Parking
4.82 per home

635 covered, 412 open

Built-up area, all floors
11,20,199 sq ft

1,04,070 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 9 RERA projects of Embassy Group on the map

The company

Registered as
SUMMIT DEVELOPMENTS LIMITED
Type
Company
Company number
U70200KA2011PLC057054

CIN or LLPIN, from the Registrar of Companies.

PAN
AAPCS4469K
GSTIN
29AAPCS4469K1ZF

Its other registrations on RERA Karnataka

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹308.4 crBuilding and development ₹1250.6 crTotal ₹1559.0 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q2 2026-27₹29.3 cr₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station17.82 kmReliable
  • Nearest railway station3.72 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.82 kmCaveat

Hospitals

  • Nearest hospital3.52 kmCaveat

Schools

  • Schools in pincode 562157 (UDISE+ census)56Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionChikkajala PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.08 kmReliable
  • Nearest sewage treatment plant6.03 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)4.93 kmCaveat
  • Nearest commercial-airport runway9.86 kmReliable
  • Distance to runway approach-path proxy1.81 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (13.18053, 77.59939), 2026-10-24. Each figure's source and caveat are in the full report.