Neighborhood IntelOpen on the map

RERA project · Plotted Development

ELEGANT MYSTIC ELITE

by ELEGANT BUILDERS AND DEVELOPERS · 79 plots · 4.00 acres · Bengaluru South

Upcoming Under construction, due Dec 2027. 74% built with 34% of the time used.

Location report

At a glance

Is it on schedule?Never extended
74% built

Due 31 Dec 2027. 34% of the time from RERA approval to the deadline has passed.

Built74%
Time used34%
How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
20 plots per acre

Similar projects within 3 km: 14 per acre. 48% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 2 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?4 due so far
0% on time

Of its 8 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 2 past due with no completion filed, 4 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jan 2026
  2. Approved by RERA17 Mar 2026
  3. Today24 Oct 2026

    34% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q4 2025-2652%
Q1 2026-2768%
Q2 2026-2774%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

12.14 x 12.19
1,600 sq ft
149 m² each
3 plots · 4% of the project
9.14 x 6.1
600 sq ft
56 m² each
9 plots · 11% of the project
odd site
1,224 sq ft
114 m² each
16 plots · 20% of the project
9.14 x 12.19
1,201 sq ft
112 m² each
49 plots · 62% of the project
9.14 x 11.92
1,168 sq ft
108 m² each
2 plots · 3% of the project

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Plots per acre

This project20
Typical within 3 km (7)14
Typical in the city (593)16

Fewer plots on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project48%
Typical within 3 km (7)47%
Typical in the city (730)46%

The share of the land not built on, which includes roads.

Land
4.00 acres

16,187 m²

Plot area (the sites)
52% of the land

8,451 m²

Roads
5,138 m²
Parks and open spaces
2,432 m²
Civic amenity sites
167 m²

Sites kept for public uses such as a school or a health centre.

CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 8 RERA projects of ELEGANT BUILDERS AND DEVELOPERS on the map

Complaints to RERA about its other projects

The company

Registered as
ELEGANT BUILDERS AND DEVELOPERS
Type
Partnership Firm
PAN
AADFE0590L
GSTIN
29AADFE0590L2Z6

Its other registrations on RERA Karnataka

7 registrations under this company
  • ELEGANT AURA PRM/KA/RERA/1251/309/PR/100125/007379 · approved 10 Jan 2025
  • ELEGANT TAKT PRM/KA/RERA/1251/309/PR/251024/007174 · approved 25 Oct 2024
  • ELEGANT HERMITAGE PRM/KA/RERA/1251/310/PR/300623/006025 · approved 30 Jun 2023
  • ELEGANT EXQUISITE PRM/KA/RERA/1251/310/PR/200817/003547 · approved 17 Aug 2020
  • ELEGANT TERRACES PRM/KA/RERA/1251/310/PR/200515/003390 · approved 15 May 2020
  • ELEGANT EXOTICA PRM/KA/RERA/1251/309/PR/190301/002457 · approved 1 Mar 2019
  • ELEGANT WHISPERING WINDS PRM/KA/RERA/1251/310/PR/171222/001523 · approved 22 Dec 2017

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹35.2 crBuilding and development ₹3.5 crTotal ₹38.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q4 2025-26₹0.0 lakh₹0.0 lakh
Q1 2026-27₹0.0 lakh₹0.0 lakh
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station5.13 kmReliable
  • Nearest railway station8.3 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.6 kmCaveat

Hospitals

  • Nearest hospital2.82 kmCaveat

Schools

  • Schools in pincode 560082 (UDISE+ census)71Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKaggalipura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)10.54 kmReliable
  • Nearest sewage treatment plant6.04 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)21.67 kmCaveat
  • Nearest commercial-airport runway44.87 kmReliable
  • Distance to runway approach-path proxy40.31 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.83264, 77.49315), 2026-10-24. Each figure's source and caveat are in the full report.