Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Elanza

by Lodha Developers Limited · 698 homes · 6.76 acres · 6 towers · Anekal

Upcoming Under construction, due Sep 2031. 2% built with 15% of the time used. 47% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
2% built

Due 30 Sep 2031. 15% of the time from RERA approval to the deadline has passed.

Built2%
Time used15%
How much is sold?367 left
47% booked

331 of 698 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
103 homes per acre

Similar projects within 3 km: 70 per acre. 33% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?Too early to tell
No deliveries yet

None of its 7 RERA projects in Bengaluru Urban has reached its deadline yet.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA19 Dec 2025
  2. Work started1 Feb 2026
  3. Today24 Oct 2026

    15% of the time to the deadline has passed.

  4. If it slips like a typical project1 Jul 2032

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-260%
Q4 2025-260%
Q1 2026-270%
Q2 2026-272%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

A2%
B2%
C2%
D1%
E1%
F1%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

331 booked367 leftQ2 2026-27

Still available: 2 × 1 BHK+STUDY+GARDEN, 74 × 3 BHK OPTIMA, 2 × 3 BHK+GARDEN_A, 3 × 3 BHK+STUDY_C, 147 × 3 BHK_B, 6 × 4 BHK+STUDY+TERRACE_PH_A, 6 × 4 BHK_A, 2 × 3 BHK_A, 104 × 3 BHK+STUDY_A, 2 × 3 BHK+STUDY_B, 3 × 4 BHK+STUDY, 6 × 4 BHK+STUDY+TERRACE_PH_B, 6 × 4 BHK_B, 2 × 2 BHK+GARDEN, 2 × 3 BHK+GARDEN_B.

Booked, by type

1 BHK+STUDY+GARDEN0 of 2
3 BHK OPTIMA98 of 172
3 BHK+GARDEN_A0 of 2
3 BHK+STUDY_C0 of 3
3 BHK_B169 of 316
4 BHK+STUDY+TERRACE_PH_A0 of 6
4 BHK_A0 of 6
3 BHK_A0 of 2
3 BHK+STUDY_A64 of 168
3 BHK+STUDY_B0 of 2
4 BHK+STUDY0 of 3
4 BHK+STUDY+TERRACE_PH_B0 of 6
4 BHK_B0 of 6
2 BHK+GARDEN0 of 2
3 BHK+GARDEN_B0 of 2

Booked, each quarter

Q3 2025-26298 of 698
Q4 2025-26281 of 698
Q1 2026-27297 of 698
Q2 2026-27331 of 698

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK_B
1,236 sq ft
115 m² carpet
37 m² land share · 1 parking space
316 homes · 45% of the project
3 BHK OPTIMA
980 sq ft
91 m² carpet
30 m² land share · 1 parking space
172 homes · 25% of the project
3 BHK+STUDY_A
1,499 sq ft
139 m² carpet
45 m² land share · 1 parking space
168 homes · 24% of the project
4 BHK_A
1,982 sq ft
184 m² carpet
60 m² land share · 1 parking space
6 homes · 1% of the project
4 BHK+STUDY+TERRACE_PH_A
3,453 sq ft
321 m² carpet
104 m² land share · 1 parking space
6 homes · 1% of the project
4 BHK_B
1,976 sq ft
184 m² carpet
60 m² land share · 1 parking space
6 homes · 1% of the project
4 BHK+STUDY+TERRACE_PH_B
4,123 sq ft
383 m² carpet
125 m² land share · 1 parking space
6 homes · 1% of the project
3 BHK+STUDY_C
1,417 sq ft
132 m² carpet
43 m² land share · 1 parking space
3 homes · 0% of the project
4 BHK+STUDY
1,677 sq ft
156 m² carpet
51 m² land share · 1 parking space
3 homes · 0% of the project
1 BHK+STUDY+GARDEN
892 sq ft
83 m² carpet
27 m² land share · 1 parking space
2 homes · 0% of the project
3 BHK+GARDEN_A
1,157 sq ft
108 m² carpet
35 m² land share · 1 parking space
2 homes · 0% of the project
3 BHK_A
1,227 sq ft
114 m² carpet
37 m² land share · 1 parking space
2 homes · 0% of the project
3 BHK+STUDY_B
1,490 sq ft
138 m² carpet
45 m² land share · 1 parking space
2 homes · 0% of the project
2 BHK+GARDEN
1,093 sq ft
102 m² carpet
33 m² land share · 1 parking space
2 homes · 0% of the project
3 BHK+GARDEN_B
1,446 sq ft
134 m² carpet
44 m² land share · 1 parking space
2 homes · 0% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

A33 floors
B33 floors
C33 floors
D33 floors
E33 floors
F33 floors

A: 119 homes, 104 m tall · B: 119 homes, 104 m tall · C: 111 homes, 104 m tall · D: 111 homes, 104 m tall · E: 119 homes, 104 m tall · F: 119 homes, 104 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project103
Typical within 3 km (81)70
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project33%
Typical within 3 km (83)67%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.76 acres

27,344 m²

Ground covered by buildings
67% of the land

18,372 m²

Floor-area ratio
2.49

Floors built per unit of land: 2.49 m² of floors for each m² of land.

Parking
1.00 per home

698 covered, 0 open

Built-up area, all floors
19,26,620 sq ft

1,78,989 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 7 RERA projects of Lodha on the map

Complaints to RERA about its other projects

The company

Registered as
Lodha Developers Limited
Type
Company
Company number
L45200MH1995PLC093041

CIN or LLPIN, from the Registrar of Companies.

PAN
AAACL1490J
GSTIN
29AAACL1490J1ZC

Its other registrations on RERA Karnataka

6 registrations under this company
  • Fiorana@Beaumont Estate(Phase-1) PRM/KA/RERA/1251/472/PR/200726/008829 · approved 20 Jul 2026
  • Haven Phase 2 PRM/KA/RERA/1251/308/PR/260326/008551 · approved 26 Mar 2026
  • Azur Phase 2 PRM/KA/RERA/1251/310/PR/200925/008110 · approved 20 Sep 2025
  • Haven PRM/KA/RERA/1251/308/PR/280525/007785 · approved 28 May 2025
  • Azur Tower D PRM/KA/RERA/1251/310/PR/280324/006746 · approved 28 Mar 2024
  • Azur PRM/KA/RERA/1251/310/PR/220324/006728 · approved 22 Mar 2024

The land is owned together with others (a joint development), including Lodha Developers Limited (formerly known as Macrotech Developers Limited).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹178.0 crBuilding and development ₹830.8 crTotal ₹1008.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹10.4 cr₹8.3 cr
Q4 2025-26₹83.7 cr₹73.8 cr
Q1 2026-27₹120.5 cr₹120.1 cr
Q2 2026-27₹150.1 cr₹147.6 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station9.67 kmReliable
  • Nearest railway station6.79 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.09 kmCaveat

Hospitals

  • Nearest hospital1.06 kmCaveat

Schools

  • Schools in pincode 562125 (UDISE+ census)91Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km6Caveat
  • Median pupil-teacher ratio, schools within 1 km20.2 :1Caveat
  • Schools with library + playground + ICT lab (1 km)1Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSarjapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)12.17 kmReliable
  • Nearest sewage treatment plant6.43 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)11.72 kmCaveat
  • Nearest commercial-airport runway34.96 kmReliable
  • Distance to runway approach-path proxy33.52 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.87471, 77.75883), 2026-10-24. Each figure's source and caveat are in the full report.