RERA project · Residential/Group Housing
DSR THE ADDRESS
by DSR INFRAPROJECTS · 702 homes · 13.68 acres · 6 towers · Anekal
Upcoming Under construction, due Jun 2029. 47% built with 45% of the time used. 21% of homes booked.
At a glance
Due 12 Jun 2029. 45% of the time from RERA approval to the deadline has passed.
290 of 1,372 homes, as the builder reported for Q1 2026-27.
Similar projects within 3 km: 76 per acre. 93% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 3 RERA projects in Bengaluru Urban: 0 delivered on time, 1 past due with no completion filed, 2 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started25 Jul 2024
- Approved by RERA5 Sep 2024
- Today24 Oct 2026
45% of the time to the deadline has passed.
- Deadline12 Jun 2029
The date it must be complete by.
- If it slips like a typical project14 Mar 2030
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q1 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 129 × 2BHK, 712 × 3BHK, 89 × 4BHK, 152 × 1BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
Tower 1: 275 homes, 3 basements · Tower 2: 275 homes, 3 basements · Tower 3: 120 homes, 3 basements · Tower 4: 275 homes, 3 basements · Tower 5: 275 homes, 3 basements · Tower 6: 152 homes, 3 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 13.68 acres
- Ground covered by buildings
- 7% of the land
- Floor-area ratio
- 204733.00
- Parking
- 1.34 per home
- Built-up area, all floors
- 15,95,856 sq ft
55,341 m²
3,922 m²
Floors built per unit of land: 204733.00 m² of floors for each m² of land.
938 covered, 0 open
1,48,260 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 3 RERA projects of DSR INFRAPROJECTS on the map
The company
- Registered as
- DSR INFRAPROJECTS
- Type
- Partnership Firm
- PAN
- AAPFD6671B
- GSTIN
- 29AAPFD6671B1Z7
- Website
- WWW.DSRINFRA.COM
Its other registrations on RERA Karnataka
- DSR THE COURTYARD PRM/KA/RERA/1251/446/PR/280324/006759 · approved 28 Mar 2024
- DSR GREEN WATERS PRM/KA/RERA/1251/446/PR/061222/005506 · approved 6 Dec 2022
- DSR HIGHLAND GREENZ PRM/KA/RERA/1251/446/PR/110522/004876 · approved 11 May 2022
- DSR VERTEX AND APEX PRM/KA/RERA/1251/446/PR/200526/003419 · approved 26 May 2020
- DSR RR AVENUES PRM/KA/RERA/1251/472/PR/190809/002785 · approved 9 Aug 2019
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/050924/006996 · Approved
- Building plan approvedBDA - Bangalore Development Authority · 18/24-25 · 18 Jul 2024
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q1 2026-27 update
- Water sourceBoreWell,Local Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
268 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q4 2025-26 | ₹24.3 cr | ₹24.3 cr |
| Q1 2026-27 | ₹19.7 cr | ₹16.5 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station9.69 kmReliable
- Nearest railway station4.99 kmReliable
- Bus stops within 500 m1Caveat
Parks, shops, daily needs
- Supermarkets within 1 km1Caveat
- Parks within 1 km2Caveat
- Nearest lake / water body (≥2 ha)0.62 kmCaveat
Hospitals
- Nearest hospital1.25 kmCaveat
Schools
- Schools in pincode 562125 (UDISE+ census)91Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionSarjapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km1Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)10.91 kmReliable
- Nearest sewage treatment plant6.34 kmCaveat
- Industrial zones within 1 km2Caveat
- Nearest airfield runway (any, incl. military)9.61 kmCaveat
- Nearest commercial-airport runway32.93 kmReliable
- Distance to runway approach-path proxy31.74 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.89228, 77.74921), 2026-10-24. Each figure's source and caveat are in the full report.