RERA project · Residential/Group Housing

DS MAX SWASTIKA

by ASHA SATISH · 68 homes · 1.00 acres · 2 towers · Bengaluru North

Upcoming Under construction, due Mar 2027. 89% built with 85% of the time used. 72% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
89% built

Due 31 Mar 2027. 85% of the time from RERA approval to the deadline has passed.

Built89%
Time used85%
How much is sold?19 left
72% booked

49 of 68 homes, as the builder reported for Q2 2026-27.

How crowded is it?About the same
68 homes per acre

Similar projects within 3 km: 74 per acre. 33% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?36 due so far
8% on time

Of its 49 RERA projects in Bengaluru Urban: 3 delivered on time, 23 late (after the date first promised), 10 past due with no completion filed, 13 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Apr 2024
  2. Approved by RERA3 May 2024
  3. Today24 Oct 2026

    85% of the time to the deadline has passed.

  4. If it slips like a typical project31 Dec 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2640%
Q4 2025-2670%
Q1 2026-2779%
Q2 2026-2789%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Building 189%
Building 289%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

49 booked19 leftQ2 2026-27

Still available: 1 × 1 BHK, 6 × 2 BHK, 12 × 3 BHK.

Booked, by type

1 BHK0 of 1
2 BHK17 of 23
3 BHK32 of 44

Booked, each quarter

Q3 2025-2645 of 68
Q4 2025-2643 of 68
Q1 2026-2734 of 68
Q2 2026-2749 of 68

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
912 sq ft
85 m² carpet · sizes 693–1,131 sq ft (8 at this size)
34 m² land share · 50 m² balcony/terrace · 1 parking space
44 homes · 65% of the project
2 BHK
693 sq ft
64 m² carpet · sizes 680–855 sq ft (14 at this size)
24 m² land share · 35 m² balcony/terrace · 1 parking space
23 homes · 34% of the project
1 BHK
529 sq ft
49 m² carpet
18 m² land share · 26 m² balcony/terrace · 1 parking space
1 home · 1% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Building 14 floors
Building 24 floors

Building 1: 10 homes, 15 m tall · Building 2: 58 homes, 15 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project68
Typical within 3 km (25)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project33%
Typical within 3 km (26)54%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
1.00 acres

4,046 m²

Ground covered by buildings
67% of the land

2,696 m²

Floor-area ratio
1.75

Floors built per unit of land: 1.75 m² of floors for each m² of land.

Parking
0.82 per home

56 covered, 0 open

Built-up area, all floors
82,408 sq ft

7,656 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 49 RERA projects of DS Max on the map

The company

Registered as
ASHA SATISH
Type
Proprietorship

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹10.0 crBuilding and development ₹12.8 crTotal ₹22.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹43.0 lakh₹43.0 lakh
Q4 2025-26₹0.0 lakh₹0.0 lakh
Q1 2026-27₹1.9 cr₹1.5 cr
Q2 2026-27₹7.3 cr₹7.3 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station5.29 kmReliable
  • Nearest railway station2.52 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)1.2 kmCaveat

Hospitals

  • Nearest hospital0.2 kmCaveat

Schools

  • Schools in pincode 560045 (UDISE+ census)156Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km36Caveat
  • Median pupil-teacher ratio, schools within 1 km25.9 :1Caveat
  • Schools with library + playground + ICT lab (1 km)13Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionGovindapura PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km3Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)8.81 kmReliable
  • Nearest sewage treatment plant1.46 kmCaveat
  • Industrial zones within 1 km10Caveat
  • Nearest airfield runway (any, incl. military)5.93 kmCaveat
  • Nearest commercial-airport runway19.47 kmReliable
  • Distance to runway approach-path proxy16.52 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)2Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)5Caveat

ReliableFrom our location report at the builder-entered pin (13.02731, 77.62040), 2026-10-24. Each figure's source and caveat are in the full report.