by DS MAX PROPERTIES PRIVATE LIMITED · 550 homes · 3.52 acres · 1 tower · Anekal

Upcoming Under construction, due Oct 2030. 10% built with 17% of the time used. 7% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
10% built

Due 31 Oct 2030. 17% of the time from RERA approval to the deadline has passed.

Built10%
Time used17%
How much is sold?511 left
7% booked

39 of 550 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
156 homes per acre

Similar projects within 3 km: 74 per acre. 75% of the land is left open.

Any complaints?See the list
1 complaint

Complaints to RERA about this project. 18 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?36 due so far
8% on time

Of its 49 RERA projects in Bengaluru Urban: 3 delivered on time, 23 late (after the date first promised), 10 past due with no completion filed, 13 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA29 Dec 2025
  2. Work started1 Jan 2026
  3. Today24 Oct 2026

    17% of the time to the deadline has passed.

  4. If it slips like a typical project2 Aug 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-260%
Q4 2025-261%
Q1 2026-277%
Q2 2026-2710%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

39 booked511 leftQ2 2026-27

Still available: 84 × 2 BHK, 427 × 3 BHK.

Booked, by type

2 BHK26 of 110
3 BHK13 of 440

Booked, each quarter

Q3 2025-260 of 550
Q4 2025-2622 of 550
Q1 2026-2732 of 550
Q2 2026-2739 of 550

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
  • 920 sq ft126 homes85.5 m²
  • 959 sq ft126 homes89.1 m²
  • 940 sq ft42 homes87.3 m²
  • 922 sq ft21 homes85.7 m²
  • and 125 homes in other sizes
Typically 26 m² land share · 15 m² balcony/terrace · 1 parking space
440 homes · 80% of the project
2 BHK
  • 737 sq ft44 homes68.5 m²
  • 799 sq ft42 homes74.2 m²
  • 807 sq ft21 homes75.0 m²
  • 750 sq ft2 homes69.7 m²
  • and 1 home in other sizes
Typically 20 m² land share · 9 m² balcony/terrace · 1 parking space
110 homes · 20% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Sky Sampada22 floors

Sky Sampada: 550 homes, 69 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project156
Typical within 3 km (23)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project75%
Typical within 3 km (23)67%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.52 acres

14,264 m²

Ground covered by buildings
25% of the land

3,605 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.10 per home

603 covered, 0 open

Built-up area, all floors
6,46,900 sq ft

60,099 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 49 RERA projects of DS Max on the map

Complaints to RERA about its other projects

18 complaints across 10 projects. The most complained about:

Show all 10 projects
  • DS MAX SONATA NEST 1 complaint
  • DS MAX SYNERGY 1 complaint
  • DS MAX SKY SANMAN 1 complaint
  • DS MAX SKY STANZA 1 complaint
  • DS MAX SKY FIELDS 1 complaint

The company

Registered as
DS MAX PROPERTIES PRIVATE LIMITED
Type
Company
Company number
U70102KA2007PTC041508

CIN or LLPIN, from the Registrar of Companies.

PAN
AACCD6168M
GSTIN
29AACCD6168M1Z3

Its other registrations on RERA Karnataka

43 registrations under this company
  • DS MAX SKYSAMPURN PRM/KA/RERA/1250/304/PR/270726/008848 · approved 27 Jul 2026
  • DS MAX SKY SUKHINO PRM/KA/RERA/1251/310/PR/050526/008622 · approved 5 May 2026
  • DS MAX SPOORTHI NEST PRM/KA/RERA/1251/308/PR/230126/008427 · approved 23 Jan 2026
  • DS MAX SKY STANZA PRM/KA/RERA/1251/308/PR/281125/008287 · approved 28 Nov 2025
  • DS MAX SKY SHLOKAM PRM/KA/RERA/1251/472/PR/250225/007524 · approved 25 Feb 2025
  • DS MAX SKY FIELDS PRM/KA/RERA/1250/304/PR/251024/007179 · approved 25 Oct 2024
  • DS MAX SKY SISIRA PRM/KA/RERA/1250/301/PR/251024/007178 · approved 25 Oct 2024
  • DS MAX SKY SANMAN PRM/KA/RERA/1251/308/PR/160824/006973 · approved 16 Aug 2024
  • DS MAX SKY BLOSSOM PRM/KA/RERA/1251/310/PR/210324/006724 · approved 21 Mar 2024
  • DS MAX SKY SAMURAI PRM/KA/RERA/1250/304/PR/150224/006622 · approved 15 Feb 2024
  • DS MAX SISTA GRAND PRM/KA/RERA/1251/310/PR/151223/006489 · approved 15 Dec 2023
  • DS MAX SKY SANJEEVINI PRM/KA/RERA/1251/309/PR/060923/006244 · approved 6 Sep 2023
  • DS MAX SHRESTA PRM/KA/RERA/1251/309/PR/220223/005748 · approved 22 Feb 2023
  • DS MAX SAMYAK PRM/KA/RERA/1251/310/PR/150223/005721 · approved 15 Feb 2023
  • DS MAX STAVAM NEST PRM/KA/RERA/1251/472/PR/180722/005079 · approved 18 Jul 2022
  • DS MAX SENATE PRM/KA/RERA/1251/446/PR/110722/005059 · approved 11 Jul 2022
  • DS MAX SPOORTHI PRM/KA/RERA/1251/308/PR/290122/004660 · approved 29 Jan 2022
  • DS MAX SASMARA PRM/KA/RERA/1251/472/PR/221221/004599 · approved 22 Dec 2021
  • DS MAX STAVAM PRM/KA/RERA/1251/309/PR/211209/004576 · approved 9 Dec 2021
  • DS MAX SKY SHUBHAM PRM/KA/RERA/1251/446/PR/210312/004002 · approved 12 Mar 2021
  • DS MAX SAHARA PRM/KA/RERA/1251/308/PR/201201/003733 · approved 1 Dec 2020
  • DS MAX SONATA NEST PRM/KA/RERA/1251/309/PR/201106/003686 · approved 6 Nov 2020
  • DS MAX SUNWORTH PRM/KA/RERA/1251/446/PR/190823/002823 · approved 23 Aug 2019
  • DS MAX SOVEREIGN PRM/KA/RERA/1251/446/PR/190722/002710 · approved 22 Jul 2019
  • DS-MAX SKY SUPREME PRM/KA/RERA/1251/310/PR/190328/002502 · approved 28 Mar 2019
  • SANGAM GRAND PRM/KA/RERA/1251/446/PR/190301/002464 · approved 1 Mar 2019
  • SKY GRAND PRM/KA/RERA/1251/446/PR/190130/002312 · approved 30 Jan 2019
  • Sankalp Manor PRM/KA/RERA/1251/446/PR/181226/002241 · approved 26 Dec 2018
  • DS MAX SYNERGY PRM/KA/RERA/1251/309/PR/181122/002151 · approved 22 Nov 2018
  • DS-Max Sarovar PRM/KA/RERA/1251/308/PR/180518/001733 · approved 18 May 2018
  • DS MAX Skyscape PRM/KA/RERA/1251/446/PR/180516/001706 · approved 16 May 2018
  • DS MAX SAVERA PRM/KA/RERA/1251/310/PR/180516/001702 · approved 16 May 2018
  • DS MAX Smartnest PRM/KA/RERA/1251/309/PR/180516/001703 · approved 16 May 2018
  • DS MAX Silver Oak PRM/KA/RERA/1251/308/PR/180516/001704 · approved 16 May 2018
  • DS Max Silverwood PRM/KA/RERA/1251/308/PR/180516/001705 · approved 16 May 2018
  • DS - Max Sparkle Nest PRM/KA/RERA/1251/446/PR/180516/001707 · approved 16 May 2018
  • DS-MAX STAR LINE PRM/KA/RERA/1251/310/PR/180313/001980 · approved 13 Mar 2018
  • DSMAX SKYCITY PRM/KA/RERA/1251/309/PR/180120/001878 · approved 20 Jan 2018
  • DS MAX SATELLITE PRM/KA/RERA/1251/310/PR/180120/001819 · approved 20 Jan 2018
  • DS MAX SPLENDID PRM/KA/RERA/1251/309/PR/180120/001707 · approved 20 Jan 2018
  • DS MAX SKY CLASSIC PRM/KA/RERA/1251/308/PR/180120/001520 · approved 20 Jan 2018
  • DS MAX SONATA PRM/KA/RERA/1251/309/PR/180120/001403 · approved 20 Jan 2018
  • DS MAX STARRY PRM/KA/RERA/1251/308/PR/171222/001477 · approved 22 Dec 2017

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹20.0 crBuilding and development ₹108.8 crTotal ₹128.6 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹0.0 lakh₹0.0 lakh
Q4 2025-26₹1.9 cr₹1.9 cr
Q1 2026-27₹1.2 cr₹1.2 cr
Q2 2026-27₹2.0 cr₹2.0 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station8.52 kmReliable
  • Nearest railway station6.22 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.53 kmCaveat

Hospitals

  • Nearest hospital1.71 kmCaveat

Schools

  • Schools in pincode 562107 (UDISE+ census)71Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)0Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionAttibele PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)15.11 kmReliable
  • Nearest sewage treatment plant3.06 kmCaveat
  • Industrial zones within 1 km31Caveat
  • Nearest airfield runway (any, incl. military)21.04 kmCaveat
  • Nearest commercial-airport runway46.13 kmReliable
  • Distance to runway approach-path proxy44.82 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.77271, 77.75084), 2026-10-24. Each figure's source and caveat are in the full report.