DISHA PURSUIT OF THE ELEMENTS PHASE 1
by Dishahabitat Projects LLP · 843 homes · 12.00 acres · 5 towers · Anekal
Upcoming Under construction, due Dec 2027. 73% built with 68% of the time used. 79% of homes booked.
At a glance
Due 31 Dec 2027. 68% of the time from RERA approval to the deadline has passed.
663 of 843 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 80 per acre. 75% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 3 RERA projects in Bengaluru Urban: 1 delivered on time, 2 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Jan 2024
- Approved by RERA28 Mar 2024
- Today24 Oct 2026
68% of the time to the deadline has passed.
- Deadline31 Dec 2027
The date it must be complete by.
- If it slips like a typical project1 Oct 2028
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 14 × 1 BHK, 13 × 3 BHK+3T+ Staff Room, 2 × 3 BHK+3T+Staff Room, 16 × 4 BHK+ 4T+Staff Room, 28 × 2 BHK, 51 × 3BHK 2T, 34 × 3BHK 3T, 2 × 4 BHK EAST FACING, 8 × 4 BHK NORTH FACING, 2 × 4 BHK WEST FACING, 4 × 5 BHK EAST FACING, 5 × 5 BHK NORTH FACING, 1 × 5 BHK WEST FACING.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 452 sq ft274 homes42.0 m²
- 963 sq ft50 homes89.5 m²
- 967 sq ft50 homes89.8 m²
- 974 sq ft50 homes90.5 m²
- 1,109 sq ft50 homes103.0 m²
- 1,111 sq ft50 homes103.2 m²
- 1,207 sq ft50 homes112.1 m²
- 791 sq ft50 homes73.5 m²
- 843 sq ft46 homes78.3 m²
- 1,690 sq ft58 homes157.0 m²
- 1,391 sq ft27 homes129.2 m²
- 1,391 sq ft26 homes129.2 m²
- 2,025 sq ft13 homes188.1 m²
- 2,356 sq ft11 homes218.9 m²
- 2,367 sq ft10 homes219.9 m²
- 2,380 sq ft9 homes221.1 m²
- 1,995 sq ft9 homes185.3 m²
- 2,014 sq ft8 homes187.1 m²
- 1,391 sq ft2 homes129.2 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower C: 274 homes, 76 m tall, 2 basements · Tower E: 113 homes, 99 m tall, 2 basements · Tower F: 198 homes, 82 m tall, 1 basement · Tower G: 198 homes, 82 m tall, 1 basement · Villas ( R1 - R60): 60 homes, 10 m tall
Amenities
- Electricity 464 m²
- CCTV Surveillance 66 m²
- Club House 7,000 m²
- Community Hall 264 m²
- Outdoor Sports facility 1,186 m²
- Indoor Sports facility 530 m²
- Swimming Pool 250 m²
- Gym 436 m²
- Parks 4,857 m²
- Power Backup 234 m²
- Water and Sanitation 724 m²
- Air Conditioning
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 12.00 acres
- Ground covered by buildings
- 25% of the land
- Floor-area ratio
- 2.25
- Parking
- 1.42 per home
- Built-up area, all floors
- 16,42,905 sq ft
48,562 m²
12,249 m²
Floors built per unit of land: 2.25 m² of floors for each m² of land.
1,117 covered, 82 open
1,52,631 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 3 RERA projects of Dishahabitat Projects LLP on the map
The company
- Registered as
- Dishahabitat Projects LLP
- Type
- Partnership Firm
- Company number
- AAU-7415
- PAN
- AARFD7369L
- GSTIN
- 29AARFD7369L1ZF
- Website
- www.dishahabitat.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Disha Pursuit of the Elements Phase II PRM/KA/RERA/1251/308/PR/060924/007003 · approved 6 Sep 2024
- DISHA PURSUIT OF SUNSHINE PRM/KA/RERA/1251/446/PR/100323/005790 · approved 10 Mar 2023
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/280324/006756 · Approved
- Building plan approvedBDA - Bangalore Development Authority · B.D.A/E.M/E.O-1/T.A-4/EAST/40/2023-24 · 14 Dec 2023
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBoreWell
Complaints to RERA about this project
None on RERA Karnataka.
Documents
285 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹77.1 cr | ₹358.6 cr |
| Q4 2025-26 | ₹23.8 cr | ₹401.2 cr |
| Q1 2026-27 | ₹21.4 cr | ₹15.4 cr |
| Q2 2026-27 | ₹26.0 cr | ₹434.4 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station6.94 kmReliable
- Nearest railway station5.39 kmReliable
- Bus stops within 500 m1Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)1.38 kmCaveat
Hospitals
- Nearest hospital1.81 kmCaveat
Schools
- Schools in pincode 560087 (UDISE+ census)55Caveat
- Median pupil-teacher ratio, schools within 1 km15.1 :1Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionVarthur PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well33.1 m below groundCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km3Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)11.72 kmReliable
- Nearest sewage treatment plant4.54 kmCaveat
- Industrial zones within 1 km4Caveat
- Nearest airfield runway (any, incl. military)8.27 kmCaveat
- Nearest commercial-airport runway29.86 kmReliable
- Distance to runway approach-path proxy28.57 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.92055, 77.75372), 2026-10-24. Each figure's source and caveat are in the full report.