RERA project · Residential/Group Housing
Deccan Habitat
by Sri. V. RANGANATH · 115 homes · 1.55 acres · 3 towers · Bengaluru North
Delivered late Completed: the builder filed for completion on 31 Dec 2023, 1,095 days after the date it first promised.
At a glance
The builder filed for completion on 31 Dec 2023, 1,095 days after the date it first promised.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 91 per acre. 68% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started1 Dec 2017
- Approved by RERA8 Feb 2018
- First promised31 Dec 2020
The date the builder gave at registration.
- Completion filed31 Dec 2023
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower 1: 20 homes, 2 basements · Tower 2: 40 homes, 2 basements · Tower 3: 55 homes, 2 basements
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.55 acres
- Ground covered by buildings
- 32% of the land
6,274 m²
2,035 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Sri. V. RANGANATH
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/309/PR/180208/002313 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Refund of Maintenance, Deposit, Compensation for non-compliance 6 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 6 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 6 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 6 Mar 2023 · Disposed Authority Fullbench
- Refund of the Deposits collected and compensation towards non compliance of orders, etc. 6 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits, maintenance charges, compensation and compliance of all the government orders 7 Mar 2023 · Disposed Authority Fullbench
- Refund of the deposits collected, Maintainence, Solar Water Heater and compensation towards Non Compliance of orders etc 7 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 7 Mar 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 5 Jun 2023 · Disposed Authority Fullbench
- Refund of Deposits collected , maintenance collected and compensation towards non compliance of Government orders 6 Jun 2023 · Disposed Authority Fullbench
- Refund of Deposits collected and compensation towards non compliance of orders 17 Jun 2023 · Disposed Authority Fullbench
- Promoter to adhere to the government rules, return deposits and maintenance collected and compensate the damages caused due to non compliances 11 Mar 2024 · Disposed Authority Fullbench
Documents
100 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹23.0 cr
- Construction
- ₹76.7 cr
- Total project cost
- ₹99.7 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station6.79 kmReliable
- Nearest railway station4.92 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km2Caveat
- Parks within 1 km2Caveat
- Nearest lake / water body (≥2 ha)0.51 kmCaveat
Hospitals
- Nearest hospital0.75 kmCaveat
Schools
- Schools in pincode 560097 (UDISE+ census)74Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
- Schools with library + playground + ICT lab (1 km)3Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionVidhyaranyapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km19Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)2.88 kmReliable
- Nearest sewage treatment plant2.77 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)5.83 kmCaveat
- Nearest commercial-airport runway18.8 kmReliable
- Distance to runway approach-path proxy11.79 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (13.09536, 77.54577), 2026-10-24. Each figure's source and caveat are in the full report.