RERA project · Residential/Group Housing

COURTYARD BY VEDANTH SURAKSHA

by VEDANTH SURAKSHA PROPERTIES · 278 homes · 4.50 acres · 3 towers · Bengaluru South

Upcoming Under construction, due Dec 2031. 13% built with 13% of the time used. 6% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
13% built

Due 31 Dec 2031. 13% of the time from RERA approval to the deadline has passed.

Built13%
Time used13%
How much is sold?261 left
6% booked

17 of 278 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
62 homes per acre

Similar projects within 3 km: 75 per acre. 58% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Dec 2025
  2. Approved by RERA9 Jan 2026
  3. Today24 Oct 2026

    13% of the time to the deadline has passed.

  4. If it slips like a typical project1 Oct 2032

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q4 2025-266%
Q1 2026-2710%
Q2 2026-2713%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A8%
Tower B10%
Tower C11%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

17 booked261 leftQ2 2026-27

Still available: 86 × 3BHK - TYPE 1, 4 × 3BHK - TYPE 1-B, 112 × 3BHK - TYPE 2, 2 × 3BHK - TYPE 2-A, 17 × 4BHK - TYPE 1, 1 × 4BHK - TYPE 1-A, 15 × 4BHK - TYPE 2, 1 × 4BHK - TYPE 2-A, 1 × 3BHK - TYPE 1-A, 1 × 3BHK - TYPE 2-C, 18 × 3BHK - TYPE 3, 1 × 3BHK - TYPE 3-A, 1 × 3BHK - TYPE 2 -B, 1 × 3BHK - TYPE 2 -C.

Booked, by type

3BHK - TYPE 13 of 89
3BHK - TYPE 1-B0 of 4
3BHK - TYPE 212 of 124
3BHK - TYPE 2-A0 of 2
4BHK - TYPE 10 of 17
4BHK - TYPE 1-A0 of 1
4BHK - TYPE 22 of 17
4BHK - TYPE 2-A0 of 1
3BHK - TYPE 1-A0 of 1
3BHK - TYPE 2-C0 of 1
3BHK - TYPE 30 of 18
3BHK - TYPE 3-A0 of 1
3BHK - TYPE 2 -B0 of 1
3BHK - TYPE 2 -C0 of 1

Booked, each quarter

Q4 2025-263 of 278
Q1 2026-2716 of 278
Q2 2026-2717 of 278

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK - TYPE 2
1,044 sq ft
97 m² carpet
61 m² land share · 13 m² balcony/terrace · 1 parking space
124 homes · 45% of the project
3BHK - TYPE 1
1,066 sq ft
99 m² carpet
62 m² land share · 12 m² balcony/terrace · 1 parking space
89 homes · 32% of the project
3BHK - TYPE 3
1,066 sq ft
99 m² carpet
62 m² land share · 13 m² balcony/terrace · 1 parking space
18 homes · 6% of the project
4BHK - TYPE 1
1,604 sq ft
149 m² carpet
94 m² land share · 17 m² balcony/terrace · 1 parking space
17 homes · 6% of the project
4BHK - TYPE 2
1,485 sq ft
138 m² carpet
87 m² land share · 20 m² balcony/terrace · 1 parking space
17 homes · 6% of the project
3BHK - TYPE 1-B
1,062 sq ft
99 m² carpet
65 m² land share · 10 m² balcony/terrace · 1 parking space
4 homes · 1% of the project
3BHK - TYPE 2-A
1,042 sq ft
97 m² carpet
78 m² land share · 12 m² balcony/terrace · 1 parking space
2 homes · 1% of the project
4BHK - TYPE 1-A
1,605 sq ft
149 m² carpet
109 m² land share · 17 m² balcony/terrace · 1 parking space
1 home · 0% of the project
4BHK - TYPE 2-A
1,482 sq ft
138 m² carpet
101 m² land share · 18 m² balcony/terrace · 1 parking space
1 home · 0% of the project
3BHK - TYPE 1-A
1,062 sq ft
99 m² carpet
61 m² land share · 10 m² balcony/terrace · 1 parking space
1 home · 0% of the project
3BHK - TYPE 2-C
1,042 sq ft
97 m² carpet
66 m² land share · 12 m² balcony/terrace · 1 parking space
1 home · 0% of the project
3BHK - TYPE 3-A
1,068 sq ft
99 m² carpet
70 m² land share · 13 m² balcony/terrace · 1 parking space
1 home · 0% of the project
3BHK - TYPE 2 -B
1,042 sq ft
97 m² carpet
66 m² land share · 12 m² balcony/terrace · 1 parking space
1 home · 0% of the project
3BHK - TYPE 2 -C
1,042 sq ft
97 m² carpet
67 m² land share · 12 m² balcony/terrace · 1 parking space
1 home · 0% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A18 floors
Tower B19 floors
Tower C19 floors

Tower A: 89 homes, 62 m tall, 1 basement · Tower B: 94 homes, 66 m tall, 1 basement · Tower C: 95 homes, 66 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project62
Typical within 3 km (64)75
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project58%
Typical within 3 km (65)52%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.50 acres

18,210 m²

Ground covered by buildings
42% of the land

7,570 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.72 per home

478 covered, 0 open

Built-up area, all floors
6,16,266 sq ft

57,253 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
VEDANTH SURAKSHA PROPERTIES
Type
Partnership Firm
PAN
AAQFV7314J
GSTIN
29AAQFV7314J1ZH
Website
www.courtyardbyvs.com

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹119.0 crBuilding and development ₹257.8 crTotal ₹376.8 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q4 2025-26₹1.2 cr₹1.2 cr
Q1 2026-27₹2.0 cr₹2.0 cr
Q2 2026-27₹4.9 cr₹4.9 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station3.85 kmReliable
  • Nearest railway station11.18 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km1Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)0.74 kmCaveat

Hospitals

  • Nearest hospital0.65 kmCaveat

Schools

  • Schools in pincode 560083 (UDISE+ census)111Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km13Caveat
  • Median pupil-teacher ratio, schools within 1 km16 :1Caveat
  • Schools with library + playground + ICT lab (1 km)9Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKonanakunte PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)26 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km1Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well10.8 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)4.05 kmReliable
  • Nearest sewage treatment plant1.69 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)12.26 kmCaveat
  • Nearest commercial-airport runway38.04 kmReliable
  • Distance to runway approach-path proxy35.01 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (12.86152, 77.58446), 2026-10-24. Each figure's source and caveat are in the full report.