by KSDB · 5.36 acres · Bengaluru South

Past due, no completion filed Past its deadline of 16 Oct 2026, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 16 Oct 2026, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Unknown
Not known

The RERA page gives no usable land area.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?5 due so far
0% on time

Of its 5 RERA projects in Bengaluru Urban: 0 delivered on time, 5 past due with no completion filed.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started18 Oct 2021
  2. Approved by RERA28 Oct 2021
  3. Deadline16 Oct 2026

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How crowded is it?

Land left open

This project26%
Typical within 3 km (24)59%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
5.36 acres

21,708 m²

Ground covered by buildings
74% of the land

16,117 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 5 RERA projects of KSDB on the map

The company

Registered as
KSDB
Type
Karnataka Slum Development Board
PAN
AAALK0136B

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Construction
₹6.8 lakh
Total project cost
₹32.9 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.53 kmReliable
  • Nearest railway station7.07 kmReliable
  • Bus stops within 500 m14Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km5Caveat
  • Parks within 1 km22Caveat
  • Nearest lake / water body (≥2 ha)1.16 kmCaveat

Hospitals

  • Nearest hospital0.3 kmCaveat

Schools

  • Schools in pincode 560069 (UDISE+ census)7Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km24Caveat
  • Median pupil-teacher ratio, schools within 1 km20 :1Caveat
  • Schools with library + playground + ICT lab (1 km)7Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionTilak Nagar PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)26 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km6Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well10 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.28 kmReliable
  • Nearest sewage treatment plant2.21 kmCaveat
  • Industrial zones within 1 km4Caveat
  • Nearest airfield runway (any, incl. military)7.03 kmCaveat
  • Nearest commercial-airport runway31.5 kmReliable
  • Distance to runway approach-path proxy28.47 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)3Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (12.91991, 77.59634), 2026-10-24. Each figure's source and caveat are in the full report.