RERA project · Mixed Development

Concorde Mayfair

by Concorde Housing Corporation Pvt Ltd · 477 homes · 3.35 acres · 5 towers · Bengaluru North

Upcoming Under construction, due Nov 2028. 41% built with 54% of the time used. 23% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
41% built

Due 30 Nov 2028. 54% of the time from RERA approval to the deadline has passed.

Built41%
Time used54%
How much is sold?366 left
23% booked

111 of 477 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
142 homes per acre

Similar projects within 3 km: 76 per acre. 61% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 2 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?5 due so far
20% on time

Of its 10 RERA projects in Bengaluru Urban: 1 delivered on time, 4 late (after the date first promised), 5 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA3 May 2024
  2. Work started15 May 2024
  3. Today24 Oct 2026

    54% of the time to the deadline has passed.

  4. If it slips like a typical project1 Sep 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2624%
Q4 2025-2632%
Q1 2026-2736%
Q2 2026-2741%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

A42%
B41%
C48%
D39%
Commercial12%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

111 booked366 leftQ2 2026-27

Still available: 13 × 2 BHK, 93 × 3 BHK, 260 × COMMERCIAL.

Booked, by type

2 BHK14 of 27
3 BHK97 of 190
COMMERCIAL0 of 260

Booked, each quarter

Q3 2025-2682 of 477
Q4 2025-2694 of 477
Q1 2026-27100 of 477
Q2 2026-27111 of 477

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

COMMERCIAL
  • 711 sq ft127 homes66.1 m²
  • 693 sq ft23 homes64.4 m²
  • 710 sq ft22 homes66.0 m²
  • 690 sq ft19 homes64.1 m²
  • and 69 homes in other sizes
Typically 21 m² land share · 26 m² balcony/terrace
260 homes · 55% of the project
3 BHK
  • 987 sq ft26 homes91.7 m²
  • 1,116 sq ft25 homes103.7 m²
  • 1,114 sq ft14 homes103.5 m²
  • 970 sq ft13 homes90.1 m²
  • and 112 homes in other sizes
Typically 36 m² land share · 34 m² balcony/terrace · 1 parking space
190 homes · 40% of the project
2 BHK
  • 787 sq ft14 homes73.1 m²
  • 775 sq ft12 homes72.0 m²
  • 850 sq ft1 home79.0 m²
Typically 29 m² land share · 28 m² balcony/terrace · 1 parking space
27 homes · 6% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

A15 floors
B15 floors
C15 floors
D15 floors
Commercial11 floors

A: 56 homes, 45 m tall, 2 basements · B: 54 homes, 45 m tall, 2 basements · C: 55 homes, 45 m tall, 2 basements · D: 52 homes, 45 m tall, 2 basements · Commercial: 260 homes, 45 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project142
Typical within 3 km (2)76
Typical in the city (114)79

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project61%
Typical within 3 km (2)72%
Typical in the city (118)63%

The share of the land not built on, which includes roads.

Land
3.35 acres

13,551 m²

Ground covered by buildings
39% of the land

5,258 m²

Floor-area ratio
3.25

Floors built per unit of land: 3.25 m² of floors for each m² of land.

Parking
0.99 per home

449 covered, 22 open

Built-up area, all floors
7,26,133 sq ft

67,460 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active mixed development projects with a land area on RERA; the comparison is ours.

Who is building it?

All 10 RERA projects of Concorde Housing Corporation Pvt Ltd on the map

Complaints to RERA about its other projects

The company

Registered as
Concorde Housing Corporation Pvt Ltd
Type
Company
Company number
U70102KA2008PTC046886

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCC4087F
GSTIN
29AADCC4087F1ZK
Website
www.concorde.in

Its other registrations on RERA Karnataka

11 registrations under this company
  • CONCORDE SIENNA PRM/KA/RERA/1251/446/PR/220626/008740 · approved 22 Jun 2026
  • CONCORDE EQUITY PHASE II PRM/KA/RERA/1265/347/PR/161225/008342 · approved 16 Dec 2025
  • Concorde Eleve PRM/KA/RERA/1251/446/PR/210325/007608 · approved 21 Mar 2025
  • Concorde Neo PRM/KA/RERA/1251/309/PR/270924/007088 · approved 27 Sep 2024
  • Concorde Antares PRM/KA/RERA/1251/309/PR/181223/006491 · approved 18 Dec 2023
  • Concorde Equity PRM/KA/RERA/1265/347/PR/151222/005525 · approved 15 Dec 2022
  • Concorde Econex PRM/KA/RERA/1251/446/PR/311022/005385 · approved 31 Oct 2022
  • CONCORDE AURIGA PRM/KA/RERA/1251/446/PR/190704/002647 · approved 4 Jul 2019
  • Concorde Luxepolis PRM/KA/RERA/1251/310/PR/181122/002139 · approved 22 Nov 2018
  • Concorde Spring Meadows PRM/KA/RERA/1251/309/PR/180227/002657 · approved 27 Feb 2018
  • Concorde Epitome PRM/KA/RERA/1251/308/PR/171015/000698 · approved 15 Oct 2017

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹90.1 crBuilding and development ₹222.9 crTotal ₹312.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹13.0 cr₹15.2 cr
Q4 2025-26₹22.6 cr₹22.5 cr
Q1 2026-27₹23.3 cr₹23.0 cr
Q2 2026-27₹14.4 cr₹14.7 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station9.47 kmReliable
  • Nearest railway station1.13 kmReliable
  • Bus stops within 500 m7Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km4Caveat
  • Nearest lake / water body (≥2 ha)1.1 kmCaveat

Hospitals

  • Nearest hospital0.18 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km17Caveat
  • Median pupil-teacher ratio, schools within 1 km25 :1Caveat
  • Schools with library + playground + ICT lab (1 km)9Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionYelahanka PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km2Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well16.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)5.5 kmReliable
  • Nearest sewage treatment plant0.65 kmCaveat
  • Industrial zones within 1 km3Caveat
  • Nearest airfield runway (any, incl. military)2.08 kmCaveat
  • Nearest commercial-airport runway14.52 kmReliable
  • Distance to runway approach-path proxy9.2 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (13.09575, 77.59635), 2026-10-24. Each figure's source and caveat are in the full report.