by Concorde Housing Corporation Pvt Ltd · 110 homes · 1.17 acres · 1 tower · Bengaluru East

Delivered on time Completed: the builder filed for completion on 18 Mar 2026, by the date it promised.

Location report

At a glance

Was it on time?Delivered on time
Completed

The builder filed for completion on 18 Mar 2026, by the date it promised.

How much is sold?86 left
22% booked

24 of 110 homes, as the builder reported for Q3 2025-26.

How crowded is it?More crowded
94 homes per acre

Similar projects within 3 km: 36 per acre. 54% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 2 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?5 due so far
20% on time

Of its 10 RERA projects in Bengaluru Urban: 1 delivered on time, 4 late (after the date first promised), 5 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started2 May 2022
  2. Approved by RERA31 Oct 2022
  3. Completion filed18 Mar 2026

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

How much is built, each quarter

Q3 2025-26100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

24 booked86 leftQ3 2025-26

Still available: 86 × COMMERCIAL.

Booked, by type

COMMERCIAL24 of 110

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

COMMERCIAL
891 sq ft
83 m² carpet · sizes 483–1,140 sq ft (36 at this size)
44 m² land share · 33 m² balcony/terrace · 2 parking spaces
110 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

A7 floors

A: 110 homes, 27 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project94
Typical within 3 km (5)36
Typical in the city (76)14

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project54%
Typical within 3 km (5)63%
Typical in the city (76)64%

The share of the land not built on, which includes roads.

Land
1.17 acres

4,752 m²

Ground covered by buildings
46% of the land

2,181 m²

Floor-area ratio
2.24

Floors built per unit of land: 2.24 m² of floors for each m² of land.

Parking
3.89 per home

195 covered, 19 open

Built-up area, all floors
1,14,560 sq ft

10,643 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active commercial projects with a land area on RERA; the comparison is ours.

Who is building it?

All 10 RERA projects of Concorde Housing Corporation Pvt Ltd on the map

Complaints to RERA about its other projects

The company

Registered as
Concorde Housing Corporation Pvt Ltd
Type
Company
Company number
U70102KA2008PTC046886

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCC4087F
GSTIN
29AADCC4087F1ZK
Website
www.concordegroup.in

Its other registrations on RERA Karnataka

11 registrations under this company
  • CONCORDE SIENNA PRM/KA/RERA/1251/446/PR/220626/008740 · approved 22 Jun 2026
  • CONCORDE EQUITY PHASE II PRM/KA/RERA/1265/347/PR/161225/008342 · approved 16 Dec 2025
  • Concorde Eleve PRM/KA/RERA/1251/446/PR/210325/007608 · approved 21 Mar 2025
  • Concorde Neo PRM/KA/RERA/1251/309/PR/270924/007088 · approved 27 Sep 2024
  • Concorde Mayfair PRM/KA/RERA/1251/309/PR/030524/006839 · approved 3 May 2024
  • Concorde Antares PRM/KA/RERA/1251/309/PR/181223/006491 · approved 18 Dec 2023
  • Concorde Equity PRM/KA/RERA/1265/347/PR/151222/005525 · approved 15 Dec 2022
  • CONCORDE AURIGA PRM/KA/RERA/1251/446/PR/190704/002647 · approved 4 Jul 2019
  • Concorde Luxepolis PRM/KA/RERA/1251/310/PR/181122/002139 · approved 22 Nov 2018
  • Concorde Spring Meadows PRM/KA/RERA/1251/309/PR/180227/002657 · approved 27 Feb 2018
  • Concorde Epitome PRM/KA/RERA/1251/308/PR/171015/000698 · approved 15 Oct 2017

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹26.6 crBuilding and development ₹55.5 crTotal ₹82.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹1.1 cr₹1.0 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.6 kmReliable
  • Nearest railway station4.44 kmReliable
  • Bus stops within 500 m3Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km5Caveat
  • Parks within 1 km10Caveat
  • Nearest lake / water body (≥2 ha)0.95 kmCaveat

Hospitals

  • Nearest hospital0.34 kmCaveat

Schools

  • Schools in pincode 560048 (UDISE+ census)39Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km1Caveat
  • Schools with library + playground + ICT lab (1 km)0Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionMahadevapura PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)10.9 kmReliable
  • Nearest sewage treatment plant1.38 kmCaveat
  • Industrial zones within 1 km22Caveat
  • Nearest airfield runway (any, incl. military)3.66 kmCaveat
  • Nearest commercial-airport runway23.65 kmReliable
  • Distance to runway approach-path proxy23.2 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.97561, 77.70751), 2026-10-24. Each figure's source and caveat are in the full report.