CM 1 Lakh Multi Storey Bengaluru Housing

by Rajiv Gandhi Housing Corporation Limited · 332 homes · 3.00 acres · Bengaluru East

Past due, no completion filed Past its deadline of 7 Mar 2024, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 7 Mar 2024, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
111 homes per acre

Similar projects within 3 km: 70 per acre. 22% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 4 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?23 due so far
0% on time

Of its 23 RERA projects in Bengaluru Urban: 0 delivered on time, 23 past due with no completion filed.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started7 Mar 2019
  2. Approved by RERA2 Mar 2021
  3. Deadline7 Mar 2024

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

1 BHK
323 sq ft
30 m² carpet on average
332 homes · 100% of the project

Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. The builder filed the carpet area of all homes of a type together, so sizes marked "on average" are that total divided by the number of homes.

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project111
Typical within 3 km (70)70
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project22%
Typical within 3 km (72)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.00 acres

12,140 m²

Ground covered by buildings
30% of the land

3,644 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 23 RERA projects of Rajiv Gandhi Housing Corporation Limited on the map

Complaints to RERA about its other projects

The company

Registered as
Rajiv Gandhi Housing Corporation Limited
Type
Rajiv Gandhi Housing Corporation Limited
PAN
AABCR5689N

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Construction
₹28.6 cr
Total project cost
₹28.6 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station7.46 kmReliable
  • Nearest railway station6.03 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km3Caveat
  • Nearest lake / water body (≥2 ha)1.4 kmCaveat

Hospitals

  • Nearest hospital1.92 kmCaveat

Schools

  • Schools in pincode 560077 (UDISE+ census)123Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
  • Schools with library + playground + ICT lab (1 km)4Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKothanur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)4.53 kmReliable
  • Nearest sewage treatment plant2.44 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)7.07 kmCaveat
  • Nearest commercial-airport runway13.89 kmReliable
  • Distance to runway approach-path proxy12.74 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.06635, 77.66553), 2026-10-24. Each figure's source and caveat are in the full report.