RERA project · Residential/Group Housing
Century Mirai Ph1
by Century Silicon City Private Limited · 475 homes · 9.40 acres · 5 towers · Bengaluru East
Upcoming Under construction, due Oct 2030. 11% built with 20% of the time used. 45% of homes booked.
At a glance
Due 30 Oct 2030. 20% of the time from RERA approval to the deadline has passed.
215 of 475 homes, as the builder reported for Q2 2026-27.
Similar projects across the city: 76 per acre. 80% of the land is left open.
Complaints to RERA about this project.
No litigation on the land or the project, as the builder declares it to RERA.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Oct 2025
- Approved by RERA18 Oct 2025
- Today24 Oct 2026
20% of the time to the deadline has passed.
- Deadline30 Oct 2030
The date it must be complete by.
- If it slips like a typical project1 Aug 2031
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 17 × 2 BHK, 198 × 3 BHK, 36 × 4 BHK, 6 × 5 BHK, 2 × 1 BHK, 1 × 6 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 1,014 sq ft36 homes94.2 m²
- 1,181 sq ft36 homes109.7 m²
- 1,406 sq ft36 homes130.6 m²
- 1,486 sq ft36 homes138.1 m²
- and 202 homes in other sizes
- 832 sq ft66 homes77.3 m²
- 1,850 sq ft12 homes171.9 m²
- 1,941 sq ft12 homes180.3 m²
- 1,844 sq ft6 homes171.3 m²
- 2,102 sq ft3 homes195.3 m²
- and 20 homes in other sizes
- 3,229 sq ft3 homes300.0 m²
- 2,464 sq ft2 homes228.9 m²
- 3,302 sq ft1 home306.8 m²
- 750 sq ft1 home69.7 m²
- 802 sq ft1 home74.5 m²
- 3,947 sq ft1 home366.7 m²
- 4,118 sq ft1 home382.6 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower 01: 89 homes, 42 m tall, 3 basements · Tower 02: 102 homes, 42 m tall, 3 basements · Tower 03: 102 homes, 42 m tall, 3 basements · Tower 04: 91 homes, 42 m tall, 3 basements · 5: 91 homes, 42 m tall, 3 basements
Amenities
- Electricity 547 m²
- Smart Home Automation
- CCTV Surveillance
- Club House 2,312 m²
- Community Hall 276 m²
- Outdoor Sports facility 1,050 m²
- Indoor Sports facility 816 m²
- Swimming Pool 454 m²
- Gym 392 m²
- Parks 5,970 m²
- Power Backup 334 m²
- Water and Sanitation 929 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 9.40 acres
- Ground covered by buildings
- 20% of the land
- Floor-area ratio
- 3.00
- Parking
- 1.20 per home
- Built-up area, all floors
- 18,15,956 sq ft
38,033 m²
7,574 m²
Floors built per unit of land: 3.00 m² of floors for each m² of land.
570 covered, 0 open
1,68,708 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- Century Silicon City Private Limited
- Type
- Company
- Company number
- U68100KA2023PTC173682
- PAN
- AALCC0361L
- GSTIN
- 29AALCC0361L1ZE
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/181025/008182 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · BBMP/Addl.Dir/JDNORTH/0009/25-26 · 29 Aug 2025
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBWSSB
Complaints to RERA about this project
None on RERA Karnataka.
Documents
172 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹27.5 cr | ₹19.2 cr |
| Q4 2025-26 | ₹55.9 cr | ₹21.2 cr |
| Q1 2026-27 | ₹45.0 cr | ₹31.5 cr |
| Q2 2026-27 | ₹51.1 cr | ₹36.8 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.