RERA project · Residential/Group Housing
Casagrand Keatsway
by CASA GRANDE GARDEN CITY BUILDERS PVT LTD · 286 homes · 3.79 acres · 1 tower · Bengaluru East
Upcoming Under construction, due Nov 2026. 95% built with 99% of the time used. 100% of homes booked.
At a glance
Due 5 Nov 2026. 99% of the time from RERA approval to the deadline has passed.
286 of 286 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 76 per acre. 77% of the land is left open.
Complaints to RERA about this project. 165 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 22 RERA projects in Bengaluru Urban: 1 delivered on time, 3 late (after the date first promised), 7 past due with no completion filed, 11 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started20 Dec 2022
- Approved by RERA23 Dec 2022
- Today24 Oct 2026
99% of the time to the deadline has passed.
- Deadline5 Nov 2026
The date it must be complete by.
- If it slips like a typical project7 Aug 2027
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Ketsway: 286 homes, 33 m tall, 1 basement
Amenities
- Electricity 5 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 3.79 acres
- Ground covered by buildings
- 23% of the land
- Floor-area ratio
- 2.25
- Parking
- 1.09 per home
- Built-up area, all floors
- 4,90,134 sq ft
15,335 m²
3,480 m²
Floors built per unit of land: 2.25 m² of floors for each m² of land.
284 covered, 29 open
45,535 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 22 RERA projects of Casagrand on the map
Complaints to RERA about its other projects
165 complaints across 13 projects. The most complained about:
- Casagrand Orlena 103 complaints
- Casagrand Meridian 13 complaints
- Casagrand Florella 12 complaints
- Casa Grande Lorenza 7 complaints
- CASAGRAND HAZEN 7 complaints
Show all 13 projects
- CASAGRAND ZAIDEN 5 complaints
- CASAGRAND AQUENE 5 complaints
- CASAGRAND GALILEO 4 complaints
- Casagrand Royce 3 complaints
- Casagrand Florella Phase 2 2 complaints
- CASAGRAND VIVACITY 2 complaints
- CASAGRAND AMOR 1 complaint
- CASAGRAND MOONDANCE 1 complaint
The company
- Registered as
- CASA GRANDE GARDEN CITY BUILDERS PVT LTD
- Type
- Company
- Company number
- U45205KA2015PTC082415
- PAN
- AAGCC1577R
- GSTIN
- 29AAGCC1577R1ZV
- Website
- https://www.casagrand.co.in/
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
18 registrations under this company
- CASAGRAND MOONDANCE PRM/KA/RERA/1251/310/PR/200526/008667 · approved 20 May 2026
- CASAGRAND ESTANCIA PRM/KA/RERA/1251/472/PR/110925/008086 · approved 11 Sep 2025
- CASAGRAND PROMENADE PRM/KA/RERA/1251/309/PR/070525/007719 · approved 7 May 2025
- CASAGRAND VIVACITY PRM/KA/RERA/1251/308/PR/220424/006830 · approved 22 Apr 2024
- CASAGRAND REGAL PRM/KA/RERA/1251/446/PR/280324/006768 · approved 28 Mar 2024
- CASAGRAND AMOR PRM/KA/RERA/1251/310/PR/140324/006701 · approved 14 Mar 2024
- CASAGRAND FLAMINGO PRM/KA/RERA/1251/310/PR/041023/006307 · approved 4 Oct 2023
- CASAGRAND ZAIDEN PRM/KA/RERA/1251/310/PR/120423/005862 · approved 12 Apr 2023
- Casagrand Meridian PRM/KA/RERA/1251/446/PR/181122/005482 · approved 18 Nov 2022
- CASAGRAND HAZEN PRM/KA/RERA/1251/310/PR/220722/005099 · approved 22 Jul 2022
- CASAGRAND AQUENE PRM/KA/RERA/1251/310/PR/210422/004845 · approved 21 Apr 2022
- CASAGRAND GALILEO PRM/KA/RERA/1251/309/PR/070222/004675 · approved 7 Feb 2022
- Casagrand Orlena PRM/KA/RERA/1251/446/PR/210928/004324 · approved 28 Sep 2021
- Casagrand Florella Phase 2 PRM/KA/RERA/1251/308/PR/210819/004281 · approved 19 Aug 2021
- Casagrand Florella PRM/KA/RERA/1251/308/PR/210319/004044 · approved 19 Mar 2021
- Casa Grande Lorenza PRM/KA/RERA/1251/472/PR/181130/002193 · approved 30 Nov 2018
- Casagrand Royce PRM/KA/RERA/1251/446/PR/171207/002464 · approved 7 Dec 2017
- Casa Grande Neona PRM/KA/RERA/1251/446/PR/171017/000978 · approved 17 Oct 2017
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/231222/005555 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · BBMP/CC/9016/22-23 · 3 Dec 2022
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceBWSSB
Complaints to RERA about this project
- Unfair Trade Practices & Denial of Legitimate Referral Payout by Casagrand 15 Mar 2025 · Disposed Authority Bench4
- Violates Section 14 of RERA Act and Section 171 of CGST Act (benefit of ITC must be passed on, not charged) 24 Nov 2025 · Disposed Authority Bench4
- False Payment Demands before stage completion and Veracity of advertisements early project completion promises 2 Dec 2025 · Disposed Ao
Documents
146 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹183.4 cr | ₹3.2 cr |
| Q4 2025-26 | ₹185.7 cr | ₹0.0 lakh |
| Q1 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
| Q2 2026-27 | ₹0.0 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station6.57 kmReliable
- Nearest railway station4.8 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km4Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)1.9 kmCaveat
Hospitals
- Nearest hospital0.97 kmCaveat
Schools
- Schools in pincode 560077 (UDISE+ census)123Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km14Caveat
- Median pupil-teacher ratio, schools within 1 km21.6 :1Caveat
- Schools with library + playground + ICT lab (1 km)7Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionHennur PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km2Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)yesCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)6 kmReliable
- Nearest sewage treatment plant0.86 kmCaveat
- Industrial zones within 1 km3Caveat
- Nearest airfield runway (any, incl. military)5.24 kmCaveat
- Nearest commercial-airport runway16.48 kmReliable
- Distance to runway approach-path proxy14.33 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)2Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat
ReliableFrom our location report at the builder-entered pin (13.04894, 77.63986), 2026-10-24. Each figure's source and caveat are in the full report.