Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Brigade Horizon

by Brigade Enterprises Limited · 372 homes · 5.00 acres · 18 towers · Bengaluru South

Upcoming Under construction, due Dec 2026. 100% built with 96% of the time used. 99% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
100% built

Due 31 Dec 2026. 96% of the time from RERA approval to the deadline has passed.

Built100%
Time used96%
How much is sold?4 left
99% booked

368 of 372 homes, as the builder reported for Q2 2026-27.

How crowded is it?About the same
74 homes per acre

Similar projects within 3 km: 80 per acre. 67% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 44 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?35 due so far
0% on time

Of its 55 RERA projects in Bengaluru Urban: 0 delivered on time, 23 late (after the date first promised), 12 past due with no completion filed, 18 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started24 Jun 2022
  2. Approved by RERA19 Jul 2022
  3. Today24 Oct 2026

    96% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-26100%
Q4 2025-26100%
Q1 2026-27100%
Q2 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower A95%
Tower B95%
Tower C100%
Tower D100%
Tower E100%
Tower F100%
Tower G100%
Tower H100%
Tower I100%
Tower J100%
Tower K100%
Tower L100%
Tower M100%
Tower N100%
Tower O100%
Tower P100%
Tower Q100%
Tower R100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

368 booked4 leftQ2 2026-27

Still available: 4 × 4 BHK.

Booked, by type

3 BHK109 of 109
4 BHK2 of 6
2 BHK207 of 207
1 BHK50 of 50

Booked, each quarter

Q3 2025-26368 of 372
Q4 2025-26368 of 372
Q1 2026-27368 of 372
Q2 2026-27368 of 372

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2 BHK
670 sq ft
62 m² carpet · sizes 633–670 sq ft (168 at this size)
54 m² land share · 4 m² balcony/terrace · 1 parking space
207 homes · 56% of the project
3 BHK
916 sq ft
85 m² carpet · sizes 916–991 sq ft (71 at this size)
54 m² land share · 8 m² balcony/terrace · 1 parking space
109 homes · 29% of the project
1 BHK
414 sq ft
38 m² carpet
31 m² land share · 1 parking space
50 homes · 13% of the project
4 BHK
1,660 sq ft
154 m² carpet · sizes 1,660–1,725 sq ft (4 at this size)
112 m² land share · 42 m² balcony/terrace · 1 parking space
6 homes · 2% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower A9 floors
Tower B9 floors
Tower C3 floors
Tower D3 floors
Tower E4 floors
Tower F4 floors
Tower G4 floors
Tower H4 floors
Tower I4 floors
Tower J4 floors
Tower K4 floors
Tower L4 floors
Tower M4 floors
Tower N4 floors
Tower O4 floors
Tower P4 floors
Tower Q4 floors
Tower R4 floors

Tower A: 35 homes, 29 m tall, 1 basement · Tower B: 34 homes, 29 m tall, 1 basement · Tower C: 14 homes, 15 m tall, 1 basement · Tower D: 13 homes, 15 m tall, 1 basement · Tower E: 19 homes, 15 m tall, 1 basement · Tower F: 12 homes, 15 m tall · Tower G: 20 homes, 15 m tall · Tower H: 25 homes, 15 m tall · Tower I: 15 homes, 15 m tall · Tower J: 20 homes, 15 m tall · Tower K: 25 homes, 15 m tall · Tower L: 20 homes, 15 m tall · Tower M: 17 homes, 15 m tall · Tower N: 21 homes, 15 m tall · Tower O: 20 homes, 15 m tall · Tower P: 27 homes, 15 m tall · Tower Q: 15 homes, 15 m tall · Tower R: 20 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project74
Typical within 3 km (30)80
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project67%
Typical within 3 km (32)58%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
5.00 acres

20,234 m²

Ground covered by buildings
33% of the land

6,756 m²

Floor-area ratio
1.86

Floors built per unit of land: 1.86 m² of floors for each m² of land.

Parking
1.08 per home

388 covered, 14 open

Built-up area, all floors
5,87,978 sq ft

54,625 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 55 RERA projects of Brigade Group on the map

Complaints to RERA about its other projects

44 complaints across 20 projects. The most complained about:

Show all 20 projects
  • Brigade Buena Vista-Phase 2 2 complaints
  • Brigade Woods 2 complaints
  • Brigade Parkside East 2 complaints
  • Brigade 7 Gardens 2 complaints
  • Brigade Laguna 2 complaints
  • Brigade Parkside North 2 complaints
  • Brigade Northridge Neo 2 complaints
  • Brigade Oasis - Phase 3 2 complaints
  • Brigade Oak Tree Place 2 complaints
  • Brigade Lakefront - Crimson 1 complaint
  • Plumeria Phase 1 at Brigade Meadows 1 complaint
  • Brillio and Commercial at Brigade Valencia 1 complaint
  • Brigade Eternia 1 complaint
  • BRIGADE KOMARLA HEIGHTS 1 complaint
  • Brigade Oasis - Phase 1 1 complaint

The company

Registered as
Brigade Enterprises Limited
Type
Company
Company number
L85110KA1995PLC019126

CIN or LLPIN, from the Registrar of Companies.

PAN
AAACB7459F
GSTIN
29AAACB7459F1ZI
Website
www.brigadegroup.com

Its other registrations on RERA Karnataka

47 registrations under this company
  • Azalea at Brigade Meadows PRM/KA/RERA/1251/310/PR/180826/008875 · approved 18 Aug 2026
  • Brigade Misty Greens PRM/KA/RERA/1268/378/PR/100726/008806 · approved 10 Jul 2026
  • Brigade Belvedere PRM/KA/RERA/1251/446/PR/240326/008549 · approved 24 Mar 2026
  • Brigade Lumina PRM/KA/RERA/1251/309/PR/230326/008545 · approved 23 Mar 2026
  • Brigade Avalon PRM/KA/RERA/1251/446/PR/300625/007888 · approved 30 Jun 2025
  • Brigade Lakecrest PRM/KA/RERA/1251/446/PR/240625/007866 · approved 24 Jun 2025
  • Brigade Eternia PRM/KA/RERA/1251/309/PR/070325/007559 · approved 7 Mar 2025
  • Brigade Citrine PRM/KA/RERA/1250/304/PR/131224/007287 · approved 13 Dec 2024
  • Brillio and Commercial at Brigade Valencia PRM/KA/RERA/1251/308/PR/040924/006986 · approved 4 Sep 2024
  • Brigade Oasis - Phase 3 PRM/KA/RERA/1250/303/PR/220124/006562 · approved 22 Jan 2024
  • Brigade Sanctuary PRM/KA/RERA/1251/446/PR/041123/006372 · approved 4 Nov 2023
  • Brigade Calista - Phase 2 PRM/KA/RERA/1251/446/PR/220823/006195 · approved 22 Aug 2023
  • Brigade Padmini Tech Valley - Cloud PRM/KA/RERA/1251/446/PR/110823/006147 · approved 11 Aug 2023
  • Brigade Oasis - Phase 2 PRM/KA/RERA/1250/303/PR/220223/005745 · approved 22 Feb 2023
  • Brigade Calista - Phase 1 PRM/KA/RERA/1251/446/PR/030223/005683 · approved 3 Feb 2023
  • Cielo at Brigade Valencia PRM/KA/RERA/1251/308/PR/120123/005613 · approved 12 Jan 2023
  • Brigade Oak Tree Place PRM/KA/RERA/1268/378/PR/121222/005512 · approved 12 Dec 2022
  • Brigade Oasis - Phase 1 PRM/KA/RERA/1250/303/PR/041122/005401 · approved 4 Nov 2022
  • BRIGADE NANDA HEIGHTS PRM/KA/RERA/1251/310/PR/140622/004982 · approved 14 Jun 2022
  • Brigade Senate 1 (Wing 2) PRM/KA/RERA/1251/309/PR/260522/004923 · approved 26 May 2022
  • Brigade Laguna PRM/KA/RERA/1251/309/PR/170322/004775 · approved 17 Mar 2022
  • BRIGADE KOMARLA HEIGHTS PRM/KA/RERA/1251/310/PR/140322/004754 · approved 14 Mar 2022
  • Pearl at Brigade Atmosphere PRM/KA/RERA/1250/303/PR/220207/004671 · approved 7 Feb 2022
  • Brigade Northridge Neo PRM/KA/RERA/1251/309/PR/210824/004288 · approved 24 Aug 2021
  • Brigade Gem PRM/KA/RERA/1251/446/PR/210319/004042 · approved 19 Mar 2021
  • Brigade Sapphire PRM/KA/RERA/1268/378/PR/200123/003232 · approved 23 Jan 2020
  • Brigade WTC Annexe PRM/KA/RERA/1251/309/PR/191220/003095 · approved 20 Dec 2019
  • Brigade Topaz PRM/KA/RERA/1268/378/PR/181122/002190 · approved 22 Nov 2018
  • Brigade Parkside North PRM/KA/RERA/1251/309/PR/181122/002152 · approved 22 Nov 2018
  • Plumeria Lifestyle at Brigade Meadows PRM/KA/RERA/1251/310/PR/181022/002096 · approved 22 Oct 2018
  • Brigade Deccan Heights PRM/KA/RERA/1251/309/PR/180905/002006 · approved 5 Sep 2018
  • Brigade Bricklane PRM/KA/RERA/1251/309/PR/180808/001981 · approved 8 Aug 2018
  • Brigade Triumph PRM/KA/RERA/1251/309/PR/180728/001964 · approved 28 Jul 2018
  • Brigade Parkside East PRM/KA/RERA/1251/446/PR/180621/001910 · approved 21 Jun 2018
  • Brigade Senate 1 PRM/KA/RERA/1251/309/PR/180612/001900 · approved 12 Jun 2018
  • Brigade Woods PRM/KA/RERA/1251/446/PR/180611/001895 · approved 11 Jun 2018
  • Brigade Buena Vista-Phase 2 PRM/KA/RERA/1251/446/PR/180602/001854 · approved 2 Jun 2018
  • Brigade Southfield PRM/KA/RERA/1251/310/PR/180523/001804 · approved 23 May 2018
  • Brigade Senate 2 PRM/KA/RERA/1251/309/PR/180519/001764 · approved 19 May 2018
  • Brigade Buena Vista PRM/KA/RERA/1251/446/PR/171026/000405 · approved 26 Oct 2017
  • Brigade 7 Gardens PRM/KA/RERA/1251/310/PR/171021/000508 · approved 21 Oct 2017
  • Brigade Lakefront - Crimson PRM/KA/RERA/1251/446/PR/171016/000503 · approved 16 Oct 2017
  • Plumeria Phase 1 at Brigade Meadows PRM/KA/RERA/1251/310/PR/171015/000863 · approved 15 Oct 2017
  • Brigade Symphony Block A PRM/KA/RERA/1268/378/PR/171015/000758 · approved 15 Oct 2017
  • Signature Towers PRM/KA/RERA/1251/446/PR/171015/000592 · approved 15 Oct 2017
  • Brigade Atmosphere- Phase 1 PRM/KA/RERA/1250/303/PR/170916/000497 · approved 16 Sep 2017
  • Brigade Panorama PRM/KA/RERA/1251/310/PR/170916/000125 · approved 16 Sep 2017

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹46.5 crBuilding and development ₹138.0 crTotal ₹184.5 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹17.2 cr₹0.0 lakh
Q4 2025-26₹6.6 cr₹0.0 lakh
Q1 2026-27₹11.4 cr₹0.0 lakh
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.5 kmReliable
  • Nearest railway station4.77 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km2Caveat
  • Nearest lake / water body (≥2 ha)1.71 kmCaveat

Hospitals

  • Nearest hospital0.93 kmCaveat

Schools

  • Schools in pincode 560074 (UDISE+ census)70Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKumbalagudu PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km3Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)16.22 kmReliable
  • Nearest sewage treatment plant0.74 kmCaveat
  • Industrial zones within 1 km7Caveat
  • Nearest airfield runway (any, incl. military)22.8 kmCaveat
  • Nearest commercial-airport runway42.23 kmReliable
  • Distance to runway approach-path proxy36.64 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.88591, 77.45390), 2026-10-24. Each figure's source and caveat are in the full report.