Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Brigade Calista - Phase 1

by Brigade Enterprises Ltd · 506 homes · 5.81 acres · 3 towers · Bengaluru East

Upcoming Under construction, due Jun 2027. 85% built with 85% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
85% built

Due 30 Jun 2027. 85% of the time from RERA approval to the deadline has passed.

Built85%
Time used85%
How much is sold?0 left
100% booked

506 of 506 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
87 homes per acre

Similar projects within 3 km: 68 per acre. 82% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 44 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?35 due so far
0% on time

Of its 55 RERA projects in Bengaluru Urban: 0 delivered on time, 23 late (after the date first promised), 12 past due with no completion filed, 18 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started20 Jan 2023
  2. Approved by RERA3 Feb 2023
  3. Today24 Oct 2026

    85% of the time to the deadline has passed.

  4. If it slips like a typical project31 Mar 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2670%
Q4 2025-2676%
Q1 2026-2777%
Q2 2026-2785%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower D90%
Tower E88%
Tower F86%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

506 booked0 leftQ2 2026-27

Booked, by type

1 BHK88 of 88
2 BHK110 of 110
3 BHK308 of 308

Booked, each quarter

Q3 2025-26504 of 506
Q4 2025-26506 of 506
Q1 2026-27506 of 506
Q2 2026-27506 of 506

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
  • 967 sq ft72 homes89.8 m²
  • 1,072 sq ft56 homes99.6 m²
  • 1,192 sq ft38 homes110.7 m²
  • 1,035 sq ft36 homes96.2 m²
  • and 106 homes in other sizes
Typically 46 m² land share · 4 m² balcony/terrace · 1 parking space
308 homes · 61% of the project
2 BHK
  • 773 sq ft53 homes71.8 m²
  • 809 sq ft37 homes75.2 m²
  • 813 sq ft19 homes75.5 m²
  • 827 sq ft1 home76.8 m²
Typically 35 m² land share · 4 m² balcony/terrace · 1 parking space
110 homes · 22% of the project
1 BHK
  • 445 sq ft67 homes41.3 m²
  • 437 sq ft17 homes40.6 m²
  • 367 sq ft1 home34.1 m²
  • 554 sq ft1 home51.5 m²
  • and 2 homes in other sizes
Typically 20 m² land share · 2 m² balcony/terrace · 1 parking space
88 homes · 17% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower D18 floors
Tower E18 floors
Tower F17 floors

Tower D: 185 homes, 57 m tall, 1 basement · Tower E: 148 homes, 57 m tall, 1 basement · Tower F: 173 homes, 54 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project87
Typical within 3 km (39)68
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project82%
Typical within 3 km (39)72%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
5.81 acres

23,529 m²

Ground covered by buildings
18% of the land

4,141 m²

Floor-area ratio
1.44

Floors built per unit of land: 1.44 m² of floors for each m² of land.

Parking
2.11 per home

456 covered, 79 open

Built-up area, all floors
6,92,431 sq ft

64,329 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 55 RERA projects of Brigade Group on the map

Complaints to RERA about its other projects

44 complaints across 20 projects. The most complained about:

Show all 20 projects
  • Brigade Buena Vista-Phase 2 2 complaints
  • Brigade Woods 2 complaints
  • Brigade Parkside East 2 complaints
  • Brigade 7 Gardens 2 complaints
  • Brigade Laguna 2 complaints
  • Brigade Parkside North 2 complaints
  • Brigade Northridge Neo 2 complaints
  • Brigade Oasis - Phase 3 2 complaints
  • Brigade Oak Tree Place 2 complaints
  • Brigade Lakefront - Crimson 1 complaint
  • Plumeria Phase 1 at Brigade Meadows 1 complaint
  • Brillio and Commercial at Brigade Valencia 1 complaint
  • Brigade Eternia 1 complaint
  • BRIGADE KOMARLA HEIGHTS 1 complaint
  • Brigade Oasis - Phase 1 1 complaint

The company

Registered as
Brigade Enterprises Ltd
Type
Company
Company number
L85110KA1995PLC019126

CIN or LLPIN, from the Registrar of Companies.

PAN
AAACB7459F
GSTIN
29AAACB7459F1ZI
Website
www.brigadegroup.com

Its other registrations on RERA Karnataka

47 registrations under this company
  • Azalea at Brigade Meadows PRM/KA/RERA/1251/310/PR/180826/008875 · approved 18 Aug 2026
  • Brigade Misty Greens PRM/KA/RERA/1268/378/PR/100726/008806 · approved 10 Jul 2026
  • Brigade Belvedere PRM/KA/RERA/1251/446/PR/240326/008549 · approved 24 Mar 2026
  • Brigade Lumina PRM/KA/RERA/1251/309/PR/230326/008545 · approved 23 Mar 2026
  • Brigade Avalon PRM/KA/RERA/1251/446/PR/300625/007888 · approved 30 Jun 2025
  • Brigade Lakecrest PRM/KA/RERA/1251/446/PR/240625/007866 · approved 24 Jun 2025
  • Brigade Eternia PRM/KA/RERA/1251/309/PR/070325/007559 · approved 7 Mar 2025
  • Brigade Citrine PRM/KA/RERA/1250/304/PR/131224/007287 · approved 13 Dec 2024
  • Brillio and Commercial at Brigade Valencia PRM/KA/RERA/1251/308/PR/040924/006986 · approved 4 Sep 2024
  • Brigade Oasis - Phase 3 PRM/KA/RERA/1250/303/PR/220124/006562 · approved 22 Jan 2024
  • Brigade Sanctuary PRM/KA/RERA/1251/446/PR/041123/006372 · approved 4 Nov 2023
  • Brigade Calista - Phase 2 PRM/KA/RERA/1251/446/PR/220823/006195 · approved 22 Aug 2023
  • Brigade Padmini Tech Valley - Cloud PRM/KA/RERA/1251/446/PR/110823/006147 · approved 11 Aug 2023
  • Brigade Oasis - Phase 2 PRM/KA/RERA/1250/303/PR/220223/005745 · approved 22 Feb 2023
  • Cielo at Brigade Valencia PRM/KA/RERA/1251/308/PR/120123/005613 · approved 12 Jan 2023
  • Brigade Oak Tree Place PRM/KA/RERA/1268/378/PR/121222/005512 · approved 12 Dec 2022
  • Brigade Oasis - Phase 1 PRM/KA/RERA/1250/303/PR/041122/005401 · approved 4 Nov 2022
  • Brigade Horizon PRM/KA/RERA/1251/310/PR/190722/005086 · approved 19 Jul 2022
  • BRIGADE NANDA HEIGHTS PRM/KA/RERA/1251/310/PR/140622/004982 · approved 14 Jun 2022
  • Brigade Senate 1 (Wing 2) PRM/KA/RERA/1251/309/PR/260522/004923 · approved 26 May 2022
  • Brigade Laguna PRM/KA/RERA/1251/309/PR/170322/004775 · approved 17 Mar 2022
  • BRIGADE KOMARLA HEIGHTS PRM/KA/RERA/1251/310/PR/140322/004754 · approved 14 Mar 2022
  • Pearl at Brigade Atmosphere PRM/KA/RERA/1250/303/PR/220207/004671 · approved 7 Feb 2022
  • Brigade Northridge Neo PRM/KA/RERA/1251/309/PR/210824/004288 · approved 24 Aug 2021
  • Brigade Gem PRM/KA/RERA/1251/446/PR/210319/004042 · approved 19 Mar 2021
  • Brigade Sapphire PRM/KA/RERA/1268/378/PR/200123/003232 · approved 23 Jan 2020
  • Brigade WTC Annexe PRM/KA/RERA/1251/309/PR/191220/003095 · approved 20 Dec 2019
  • Brigade Topaz PRM/KA/RERA/1268/378/PR/181122/002190 · approved 22 Nov 2018
  • Brigade Parkside North PRM/KA/RERA/1251/309/PR/181122/002152 · approved 22 Nov 2018
  • Plumeria Lifestyle at Brigade Meadows PRM/KA/RERA/1251/310/PR/181022/002096 · approved 22 Oct 2018
  • Brigade Deccan Heights PRM/KA/RERA/1251/309/PR/180905/002006 · approved 5 Sep 2018
  • Brigade Bricklane PRM/KA/RERA/1251/309/PR/180808/001981 · approved 8 Aug 2018
  • Brigade Triumph PRM/KA/RERA/1251/309/PR/180728/001964 · approved 28 Jul 2018
  • Brigade Parkside East PRM/KA/RERA/1251/446/PR/180621/001910 · approved 21 Jun 2018
  • Brigade Senate 1 PRM/KA/RERA/1251/309/PR/180612/001900 · approved 12 Jun 2018
  • Brigade Woods PRM/KA/RERA/1251/446/PR/180611/001895 · approved 11 Jun 2018
  • Brigade Buena Vista-Phase 2 PRM/KA/RERA/1251/446/PR/180602/001854 · approved 2 Jun 2018
  • Brigade Southfield PRM/KA/RERA/1251/310/PR/180523/001804 · approved 23 May 2018
  • Brigade Senate 2 PRM/KA/RERA/1251/309/PR/180519/001764 · approved 19 May 2018
  • Brigade Buena Vista PRM/KA/RERA/1251/446/PR/171026/000405 · approved 26 Oct 2017
  • Brigade 7 Gardens PRM/KA/RERA/1251/310/PR/171021/000508 · approved 21 Oct 2017
  • Brigade Lakefront - Crimson PRM/KA/RERA/1251/446/PR/171016/000503 · approved 16 Oct 2017
  • Plumeria Phase 1 at Brigade Meadows PRM/KA/RERA/1251/310/PR/171015/000863 · approved 15 Oct 2017
  • Brigade Symphony Block A PRM/KA/RERA/1268/378/PR/171015/000758 · approved 15 Oct 2017
  • Signature Towers PRM/KA/RERA/1251/446/PR/171015/000592 · approved 15 Oct 2017
  • Brigade Atmosphere- Phase 1 PRM/KA/RERA/1250/303/PR/170916/000497 · approved 16 Sep 2017
  • Brigade Panorama PRM/KA/RERA/1251/310/PR/170916/000125 · approved 16 Sep 2017

The land is owned together with others (a joint development), including ARYEEHAA REALTY LIMITED.

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹93.2 crBuilding and development ₹230.7 crTotal ₹323.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹9.1 cr₹79.6 lakh
Q4 2025-26₹35.4 cr₹10.6 cr
Q1 2026-27₹32.4 cr₹18.5 cr
Q2 2026-27₹37.8 cr₹28.4 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station7.71 kmReliable
  • Nearest railway station7.75 kmReliable
  • Bus stops within 500 m3Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km8Caveat
  • Nearest lake / water body (≥2 ha)0.83 kmCaveat

Hospitals

  • Nearest hospital2.59 kmCaveat

Schools

  • Schools in pincode 560049 (UDISE+ census)110Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionAvalahally PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)2.31 kmReliable
  • Nearest sewage treatment plant2.1 kmCaveat
  • Industrial zones within 1 km18Caveat
  • Nearest airfield runway (any, incl. military)10.29 kmCaveat
  • Nearest commercial-airport runway14.04 kmReliable
  • Distance to runway approach-path proxy13.19 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.06287, 77.73878), 2026-10-24. Each figure's source and caveat are in the full report.