Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

BODHI

by M/s Cardinal Energy and Infrastructure Private Limited. · 24 homes · 0.65 acres · 1 tower · Bengaluru South

Upcoming Under construction, due Mar 2028.

Location report

At a glance

Is it on schedule?Never extended
Due Mar 2028

35% of the time has passed. No construction update is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
37 homes per acre

Similar projects within 3 km: 71 per acre. 79% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?1 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started10 Jan 2025
  2. Approved by RERA17 Jan 2026
  3. Today24 Oct 2026

    35% of the time to the deadline has passed.

  4. If it slips like a typical project31 Dec 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

4BHK-4T Type-1
  • 2,396 sq ft6 homes222.6 m²
Typically 106 m² land share · 77 m² balcony/terrace · 2 parking spaces
6 homes · 25% of the project
4BHK-4T Type-2
  • 2,523 sq ft6 homes234.4 m²
Typically 113 m² land share · 82 m² balcony/terrace · 2 parking spaces
6 homes · 25% of the project
4BHK-4T Type-3
  • 2,396 sq ft6 homes222.6 m²
Typically 108 m² land share · 79 m² balcony/terrace · 2 parking spaces
6 homes · 25% of the project
4BHK-4T Type-4
  • 2,523 sq ft6 homes234.4 m²
Typically 112 m² land share · 82 m² balcony/terrace · 2 parking spaces
6 homes · 25% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower-113 floors

Tower-1: 24 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project37
Typical within 3 km (23)71
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project79%
Typical within 3 km (24)55%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.65 acres

2,636 m²

Ground covered by buildings
21% of the land

544 m²

Floor-area ratio
3.00

Floors built per unit of land: 3.00 m² of floors for each m² of land.

Parking
2.75 per home

37 covered, 29 open

Built-up area, all floors
1,06,035 sq ft

9,851 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of Cardinal Energy And Infrastructure Private Limited on the map

The company

Registered as
M/s Cardinal Energy and Infrastructure Private Limited.
Type
Company
Company number
U40102MH2008PTC184568

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCC7243H
GSTIN
29AADCC7243H1ZK

Its other registrations on RERA Karnataka

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹25.7 crBuilding and development ₹122.7 crTotal ₹148.4 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station0.98 kmReliable
  • Nearest railway station6.59 kmReliable
  • Bus stops within 500 m7Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km6Caveat
  • Parks within 1 km17Caveat
  • Nearest lake / water body (≥2 ha)0.6 kmCaveat

Hospitals

  • Nearest hospital0.39 kmCaveat

Schools

  • Schools in pincode 560041 (UDISE+ census)18Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km33Caveat
  • Median pupil-teacher ratio, schools within 1 km20.4 :1Caveat
  • Schools with library + playground + ICT lab (1 km)10Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionTilak Nagar PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)26 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km9Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well10 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)6.45 kmReliable
  • Nearest sewage treatment plant1.93 kmCaveat
  • Industrial zones within 1 km7Caveat
  • Nearest airfield runway (any, incl. military)6.68 kmCaveat
  • Nearest commercial-airport runway30.91 kmReliable
  • Distance to runway approach-path proxy27.88 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)3Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (12.92519, 77.59739), 2026-10-24. Each figure's source and caveat are in the full report.