RERA project · Residential/Group Housing
Bhavisha Meadows
by BHAVISHA PROPERTIES · 84 homes · 1.16 acres · 1 tower · Anekal
Past due, no completion filed Past its deadline of 31 Mar 2023, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Mar 2023, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 55% of the land is left open.
Complaints to RERA about this project. 2 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 27 RERA projects in Bengaluru Urban: 1 delivered on time, 1 late (after the date first promised), 21 past due with no completion filed, 4 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started14 Jan 2022
- Approved by RERA30 Jun 2022
- Deadline31 Mar 2023
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Bhavisha Meadows: 84 homes, 15 m tall
Amenities
- Electricity
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.16 acres
- Ground covered by buildings
- 45% of the land
- Floor-area ratio
- 1.75
- Parking
- 1.00 per home
- Built-up area, all floors
- 1,15,906 sq ft
4,677 m²
2,091 m²
Floors built per unit of land: 1.75 m² of floors for each m² of land.
84 covered, 0 open
10,768 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 27 RERA projects of Bhavisha on the map
Complaints to RERA about its other projects
- Bavisha Gardeniaa 1 complaint
- Bhavisha Bentley Goldberg Phase-1 1 complaint
The company
- Registered as
- BHAVISHA PROPERTIES
- Type
- Proprietorship Firm
Its other registrations on RERA Karnataka
15 registrations under this company
- BILVA PHASE-II BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/280325/007639 · approved 28 Mar 2025
- MEADOWS PHASE-2 BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/300924/007099 · approved 30 Sep 2024
- RAAGA BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/260924/007083 · approved 26 Sep 2024
- CASA LIFE BY BHAVISHA HOMES PRM/KA/RERA/1251/308/PR/220424/006822 · approved 22 Apr 2024
- Bhavisha Bilva PRM/KA/RERA/1251/446/PR/151223/006481 · approved 15 Dec 2023
- Bhavisha Avighna PRM/KA/RERA/1251/446/PR/271123/006437 · approved 27 Nov 2023
- Bhavisha Bentley goldberg phase 2 PRM/KA/RERA/1251/308/PR/030223/005682 · approved 3 Feb 2023
- Bhavisha Bentley Goldberg Phase-1 PRM/KA/RERA/1251/308/PR/010722/005033 · approved 1 Jul 2022
- Bavisha Greystone PRM/KA/RERA/1251/308/PR/220104/004625 · approved 4 Jan 2022
- Bavisha Greenwoods PRM/KA/RERA/1251/308/PR/211130/004557 · approved 30 Nov 2021
- BHAVISHA BENTLEY GREENS PHASE 2 PRM/KA/RERA/1251/308/PR/210928/004315 · approved 28 Sep 2021
- Bavisha Gardeniaa Phase 3 PRM/KA/RERA/1251/308/PR/210422/004144 · approved 22 Apr 2021
- Bavisha Gardeniaa Phase 2 PRM/KA/RERA/1251/308/PR/210401/004091 · approved 1 Apr 2021
- Bhavisha Bentley Greens PRM/KA/RERA/1251/308/PR/200827/003572 · approved 27 Aug 2020
- Bavisha Gardeniaa PRM/KA/RERA/1251/308/PR/200817/003549 · approved 17 Aug 2020
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/300622/005027 · Approved
- Building plan approvedLocal Planing Authority · ALN/551/2021-22 · 14 Jan 2022
- Litigation on the landNone declared
- Litigation on the projectNot stated
- Water sourceLocal Authority
Complaints to RERA about this project
- Parking slot Allocated Defect Size. 15 Jun 2024 · Disposed Ao
Documents
108 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.