RERA project · Residential/Group Housing

BELLEZEA-PHASE IV

by M/S NAMBIAR BUILDERS PVT LTD · 48 homes · 6.30 acres · 5 towers · Anekal

Upcoming Under construction, due Jan 2027, after an extension. 97% built with 97% of the time used. 58% of homes booked.

Location report

At a glance

Is it on schedule?Deadline extended
97% built

Due 11 Jan 2027. 97% of the time from RERA approval to the deadline has passed.

Built97%
Time used97%
How much is sold?20 left
58% booked

28 of 48 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
8 homes per acre

Similar projects across the city: 76 per acre. 61% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?5 due so far
40% on time

Of its 7 RERA projects in Bengaluru Urban: 2 delivered on time, 3 late (after the date first promised), 2 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started11 Apr 2018
  2. Approved by RERA21 May 2018
  3. First promised11 Apr 2023

    The date the builder gave at registration.

  4. Today24 Oct 2026

    97% of the time to the deadline has passed.

  5. If it slips like a typical project13 Oct 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2684%
Q4 2025-2687%
Q1 2026-2791%
Q2 2026-2797%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block A85%
Block B81%
Block C97%
Block D98%
Block E89%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

28 booked20 leftQ2 2026-27

Still available: 20 × 4BHK.

Booked, by type

4BHK27 of 47
5BHK1 of 1

Booked, each quarter

Q3 2025-2627 of 48
Q4 2025-2628 of 48
Q1 2026-2728 of 48
Q2 2026-2728 of 48

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

4BHK
3,833 sq ft
356 m² carpet · sizes 2,590–5,074 sq ft (9 at this size)
2 parking spaces
47 homes · 98% of the project
5BHK
5,084 sq ft
472 m² carpet
2 parking spaces
1 home · 2% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block A2 floors
Block B2 floors
Block C2 floors
Block D2 floors
Block E2 floors

Block A: 11 homes · Block B: 1 home · Block C: 10 homes · Block D: 3 homes · Block E: 23 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project8
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project61%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.30 acres

25,495 m²

Ground covered by buildings
39% of the land

9,993 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 7 RERA projects of M/S NAMBIAR BUILDERS PVT LTD on the map

Complaints to RERA about its other projects

The company

Registered as
M/S NAMBIAR BUILDERS PVT LTD
Type
Company
Company number
U45201KA2009PTC050747

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCN0664M

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹16.0 cr
Construction
₹55.8 cr
Total project cost
₹71.9 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹66.5 lakh₹1.9 cr
Q4 2025-26₹29.4 lakh₹20.6 lakh
Q1 2026-27₹13.8 lakh₹9.6 lakh
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.