RERA project · Residential/Group Housing
Aswani Aaeesha B Wing
by Aswani Properties · 176 homes · 1.31 acres · 10 towers · Bengaluru South
Past due, no completion filed Past its deadline of 31 Mar 2019, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Mar 2019, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 52% of the land is left open.
Complaints to RERA about this project. 60 more about the builder's other projects.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started6 Mar 2014
- Approved by RERA14 Oct 2017
- Deadline31 Mar 2019
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.
Towers
Block 1: 20 homes · Block 2: 16 homes · Block 3: 16 homes · Block 4: 16 homes · Block 5: 20 homes · Block 6: 20 homes · Block 7: 16 homes · Block 8: 16 homes · Block 9: 16 homes · Block 10: 20 homes
Amenities
- Electricity
- Club House
- Swimming Pool
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.31 acres
- Ground covered by buildings
- 48% of the land
5,301 m²
2,530 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of Aswani Properties on the map
Complaints to RERA about its other projects
- Aswani Aaeesha A Wing 59 complaints
- ASWANI AAEESHA A WING 1 complaint
The company
- Registered as
- Aswani Properties
- Type
- Proprietorship Firm
- PAN
- AAOFA4006C
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171014/000859 · Approved
- Building plan approvedBDA - Bangalore Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Delay of project completion and delay of amenities 25 Sep 2019 · Disposed Ao
- Delay of project completion by Aswani Properties and abruptly stopping basic needs during temporary possession period. 21 Apr 2020 · Disposed Ao
- Delay of Project completion by Aswani Properties and abruptly stopping basic needs of the projects during temporary possession. 21 Apr 2020 · Disposed Authority Fullbench
- Delay of project completion by Aswani Properties and abruptly stopping basic needs durind temporary possession period. 30 Apr 2020 · Disposed Authority Fullbench
- Delay of Project completion by Aswani Properties and abruptly stopping basic needs of the projects during temporary possession 5 May 2020 · Disposed Authority Fullbench
- Non handover of amenities as promised and non adherence to sale agreement 30 May 2020 · Disposed Authority Fullbench
- Delay of Project completion by Aswani Properties and abruptly stopping basic needs of the projects during temporary possession and now builder is absconding 15 Sep 2020 · Disposed Authority Fullbench
- Mortgage and Possession 5 May 2022 · Disposed Authority Fullbench
Documents
50 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Construction
- ₹41.2 cr
- Total project cost
- ₹41.2 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.