Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Assetz Zen & Sato

by APG TOWNSHIPS PRIVATE LIMITED · 456 homes · 6.90 acres · 4 towers · Yelahanka

Upcoming Under construction, due May 2030. 60% built with 29% of the time used. 44% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
60% built

Due 31 May 2030. 29% of the time from RERA approval to the deadline has passed.

Built60%
Time used29%
How much is sold?254 left
44% booked

202 of 456 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
66 homes per acre

Similar projects within 3 km: 82 per acre. 78% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?28 due so far
25% on time

Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA8 May 2025
  2. Work started15 May 2025
  3. Today24 Oct 2026

    29% of the time to the deadline has passed.

  4. If it slips like a typical project2 Mar 2031

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2653%
Q4 2025-2655%
Q1 2026-2757%
Q2 2026-2760%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Tower-A10%
Tower- A20%
Tower A320%
Tower A47%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

202 booked254 leftQ2 2026-27

Still available: 158 × 3 BHK, 44 × 4 BHK, 26 × 2 BHK, 26 × STUDIO.

Booked, by type

3 BHK120 of 278
4 BHK46 of 90
2 BHK18 of 44
STUDIO18 of 44

Booked, each quarter

Q3 2025-2691 of 456
Q4 2025-26145 of 456
Q1 2026-27176 of 456
Q2 2026-27202 of 456

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,469 sq ft
136 m² carpet · sizes 1,403–1,476 sq ft (106 at this size)
47 m² land share · 10 m² balcony/terrace · 1 parking space
278 homes · 61% of the project
4 BHK
1,962 sq ft
182 m² carpet
64 m² land share · 6 m² balcony/terrace · 1 parking space
90 homes · 20% of the project
2 BHK
1,188 sq ft
110 m² carpet
40 m² land share · 1 parking space
44 homes · 10% of the project
STUDIO
267 sq ft
25 m² carpet
8 m² land share
44 homes · 10% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower-A114 floors
Tower- A214 floors
Tower A314 floors
Tower A414 floors

Tower-A1: 88 homes, 45 m tall, 2 basements · Tower- A2: 140 homes, 45 m tall, 2 basements · Tower A3: 140 homes, 45 m tall, 2 basements · Tower A4: 88 homes, 45 m tall, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project66
Typical within 3 km (31)82
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project78%
Typical within 3 km (32)63%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.90 acres

27,927 m²

Ground covered by buildings
22% of the land

6,185 m²

Floor-area ratio
3.00

Floors built per unit of land: 3.00 m² of floors for each m² of land.

Parking
1.21 per home

508 covered, 44 open

Built-up area, all floors
11,61,037 sq ft

1,07,864 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 54 RERA projects of Assetz on the map

The company

Registered as
APG TOWNSHIPS PRIVATE LIMITED
Type
Company
Company number
U68100KA2023PTC182247

CIN or LLPIN, from the Registrar of Companies.

PAN
AAZCA8370M
Website
www.assetzproperty.com

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹354.4 crBuilding and development ₹409.3 crTotal ₹763.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹48.2 cr₹29.0 cr
Q4 2025-26₹44.8 cr₹32.5 cr
Q1 2026-27₹44.9 cr₹32.2 cr
Q2 2026-27₹78.9 cr₹45.5 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station14.27 kmReliable
  • Nearest railway station4.96 kmReliable
  • Bus stops within 500 m3Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km2Caveat
  • Parks within 1 km9Caveat
  • Nearest lake / water body (≥2 ha)1.04 kmCaveat

Hospitals

  • Nearest hospital0.5 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
  • Schools with library + playground + ICT lab (1 km)2Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBagalur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km27Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)2.19 kmReliable
  • Nearest sewage treatment plant4.22 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)2.43 kmCaveat
  • Nearest commercial-airport runway9.59 kmReliable
  • Distance to runway approach-path proxy6.18 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (13.12250, 77.63400), 2026-10-24. Each figure's source and caveat are in the full report.