Upcoming Under construction, due Aug 2029. 56% built with 36% of the time used. 67% of homes booked.
At a glance
Due 31 Aug 2029. 36% of the time from RERA approval to the deadline has passed.
122 of 182 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 76 per acre. 94% of the land is left open.
Complaints to RERA about this project.
The builder declares litigation on the land or the project.
Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Mar 2025
- Approved by RERA28 Mar 2025
- Today24 Oct 2026
36% of the time to the deadline has passed.
- Deadline31 Aug 2029
The date it must be complete by.
- If it slips like a typical project2 Jun 2030
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 2 × 2 BHK, 58 × 3 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
- 1,305 sq ft90 homes121.2 m²
- 1,426 sq ft90 homes132.5 m²
- 966 sq ft2 homes89.7 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower-B: 182 homes, 70 m tall, 1 basement
Amenities
- Electricity 42 m²
- CCTV Surveillance
- Club House 1,559 m²
- Community Hall
- Outdoor Sports facility 2,554 m²
- Indoor Sports facility 268 m²
- Swimming Pool 347 m²
- Gym 150 m²
- Parks 2,933 m²
- Power Backup 226 m²
- Water and Sanitation
- Air Conditioning
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.81 acres
- Ground covered by buildings
- 6% of the land
- Floor-area ratio
- 1.12
- Parking
- 1.49 per home
- Built-up area, all floors
- 5,39,379 sq ft
23,523 m²
1,525 m²
Floors built per unit of land: 1.12 m² of floors for each m² of land.
233 covered, 38 open
50,110 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 54 RERA projects of Assetz on the map
The company
- Registered as
- Infraedge Management Services Pvt Ltd
- Type
- Company
- Company number
- U74900KA2014PTC077898
- PAN
- AADCI7236G
- GSTIN
- 29AADCI7236G1ZF
- Website
- www.assetzproperty.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Assetz Trees & Tandem -Tower A PRM/KA/RERA/1251/308/PR/160426/008586 · approved 16 Apr 2026
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/280325/007636 · Approved
- Building plan approvedBDA - Bangalore Development Authority · 0 · 20 Feb 2025
- Litigation on the landNone declared
- Litigation on the projectDeclared in the Q2 2026-27 update
- Water sourceBoreWell
Complaints to RERA about this project
None on RERA Karnataka.
Documents
191 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹41.8 cr | ₹27.8 cr |
| Q4 2025-26 | ₹27.6 cr | ₹10.6 cr |
| Q1 2026-27 | ₹8.3 cr | ₹13.3 cr |
| Q2 2026-27 | ₹19.6 cr | ₹13.5 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station5.69 kmReliable
- Nearest railway station3.84 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km0Caveat
- Nearest lake / water body (≥2 ha)1.3 kmCaveat
Hospitals
- Nearest hospital3.08 kmCaveat
Schools
- Schools in pincode 560035 (UDISE+ census)45Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionSarjapura PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)7.66 kmReliable
- Nearest sewage treatment plant2.55 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)9.22 kmCaveat
- Nearest commercial-airport runway34.86 kmReliable
- Distance to runway approach-path proxy34.21 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat
ReliableFrom our location report at the builder-entered pin (12.87410, 77.71585), 2026-10-24. Each figure's source and caveat are in the full report.