RERA project · Residential/Group Housing
Assetz Soho & Sky
by APG Imperial Homes Private Limited · 114 homes · 4.51 acres · 5 towers · Yelahanka
Past due, no completion filed Past its deadline of 30 Sep 2026, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Sep 2026, and no completion is filed.
114 of 114 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 76 per acre. 78% of the land is left open.
Complaints to RERA about this project.
The builder declares litigation on the land or the project.
Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Approved by RERA25 Mar 2022
- Work started1 Apr 2022
- Deadline30 Sep 2026
Passed with no completion filed.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Wing A: 2 homes, 8 m tall, 1 basement · Wing B: 4 homes, 8 m tall, 1 basement · Wing C: 4 homes, 8 m tall, 2 basements · Wing D: 52 homes, 45 m tall, 2 basements · Wing E: 52 homes, 45 m tall, 2 basements
Amenities
- Electricity 9 m²
- CCTV Surveillance
- Club House 1,523 m²
- Community Hall 168 m²
- Outdoor Sports facility 1,181 m²
- Indoor Sports facility 280 m²
- Swimming Pool 281 m²
- Gym 170 m²
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 4.51 acres
- Ground covered by buildings
- 22% of the land
- Floor-area ratio
- 1.23
- Parking
- 3.31 per home
- Built-up area, all floors
- 4,60,727 sq ft
18,266 m²
3,942 m²
Floors built per unit of land: 1.23 m² of floors for each m² of land.
353 covered, 24 open
42,803 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 54 RERA projects of Assetz on the map
The company
- Registered as
- APG Imperial Homes Private Limited
- Type
- Company
- Company number
- U45209KA2015PTC084242
- PAN
- AAOCA0369D
- GSTIN
- 29AAOCA0369D1ZM
- Website
- www.assetzproperty.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Assetz Soho & Sky Phase 1B PRM/KA/RERA/1251/309/PR/200524/006910 · approved 20 May 2024
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/472/PR/250322/004785 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · BBMP/CC/8451/21-22 · 11 Feb 2022
- Litigation on the landNone declared
- Litigation on the projectDeclared in the Q2 2026-27 update
- Water sourceBWSSB
Complaints to RERA about this project
None on RERA Karnataka.
Documents
213 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹6.0 cr | ₹4.1 cr |
| Q4 2025-26 | ₹6.2 cr | ₹3.0 cr |
| Q1 2026-27 | ₹6.5 cr | ₹5.5 cr |
| Q2 2026-27 | ₹8.4 cr | ₹5.7 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station8.69 kmReliable
- Nearest railway station4.31 kmReliable
- Bus stops within 500 m2Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km14Caveat
- Nearest lake / water body (≥2 ha)0.93 kmCaveat
Hospitals
- Nearest hospital1.18 kmCaveat
Schools
- Schools in pincode 560064 (UDISE+ census)240Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)2Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionSampigehalli PSReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)32 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- In an IISc groundwater-critical ward (2025 outlook)yesCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km3Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)5.03 kmReliable
- Nearest sewage treatment plant0.46 kmCaveat
- Industrial zones within 1 km1Caveat
- Nearest airfield runway (any, incl. military)1.59 kmCaveat
- Nearest commercial-airport runway15.55 kmReliable
- Distance to runway approach-path proxy11.77 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)1Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat
ReliableFrom our location report at the builder-entered pin (13.07032, 77.61410), 2026-10-24. Each figure's source and caveat are in the full report.