Assetz Mizumi Reserve Tower A1 A2 A4
by APG COMMUNITY DEVELOPMENT PRIVATE LIMITED · 440 homes · 9.55 acres · 3 towers · Bengaluru South
Upcoming Under construction, due Dec 2030. 59% built with 15% of the time used. 69% of homes booked.
At a glance
Due 30 Dec 2030. 15% of the time from RERA approval to the deadline has passed.
302 of 440 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 72 per acre. 87% of the land is left open.
Complaints to RERA about this project.
The builder declares litigation on the land or the project.
Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Jan 2026
- Approved by RERA4 Feb 2026
- Today24 Oct 2026
15% of the time to the deadline has passed.
- Deadline30 Dec 2030
The date it must be complete by.
- If it slips like a typical project1 Oct 2031
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
By tower, Q2 2026-27
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 2 × 2 BHK, 114 × 3 BHK, 22 × 4 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower 1: 176 homes, 72 m tall, 2 basements · Tower 2: 176 homes, 72 m tall, 2 basements · Tower 4: 88 homes, 72 m tall, 2 basements
Amenities
- Electricity 333 m²
- CCTV Surveillance
- Club House 2,856 m²
- Community Hall 369 m²
- Outdoor Sports facility 3,487 m²
- Indoor Sports facility 629 m²
- Swimming Pool 195 m²
- Gym 156 m²
- Parks 10,283 m²
- Power Backup 246 m²
- Water and Sanitation
- Air Conditioning
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 9.55 acres
- Ground covered by buildings
- 13% of the land
- Floor-area ratio
- 80014.80
- Parking
- 1.21 per home
- Built-up area, all floors
- 13,47,447 sq ft
38,660 m²
5,006 m²
Floors built per unit of land: 80014.80 m² of floors for each m² of land.
487 covered, 44 open
1,25,182 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 54 RERA projects of Assetz on the map
The company
- Registered as
- APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
- Type
- Company
- Company number
- U45203KA2014PTC077653
- PAN
- AANCA1479M
- GSTIN
- 29AANCA1479M1ZZ
- Website
- www.Assetsproperty.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
- Assetz Mizumi Reserve Tower A3 A5 PRM/KA/RERA/1251/308/PR/130526/008650 · approved 13 May 2026
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/040226/008450 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike · GBA/BSCC/Addl.CTP/0001/25-26 · 31 Jan 2026
- Litigation on the landDeclared by the builder
- Litigation on the projectDeclared in the Q2 2026-27 update
- Water sourceBWSSB
Complaints to RERA about this project
None on RERA Karnataka.
Documents
500 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q4 2025-26 | ₹115.5 cr | ₹70.5 cr |
| Q1 2026-27 | ₹67.7 cr | ₹46.4 cr |
| Q2 2026-27 | ₹85.9 cr | ₹59.9 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station1.3 kmReliable
- Nearest railway station5.94 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km2Caveat
- Parks within 1 km5Caveat
- Nearest lake / water body (≥2 ha)0.74 kmCaveat
Hospitals
- Nearest hospital0.53 kmCaveat
Schools
- Schools in pincode 560068 (UDISE+ census)144Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km10Caveat
- Median pupil-teacher ratio, schools within 1 km24.6 :1Caveat
- Schools with library + playground + ICT lab (1 km)7Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionparappana AgraharaReliable
Air quality
- PM2.5, recent 24 h avg (nearest CPCB station)18 µg/m³Caveat
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km2Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
- Groundwater depth at nearest CGWB well1 m below groundCaveat
- In an IISc groundwater-critical ward (2025 outlook)noCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)1.4 kmReliable
- Nearest sewage treatment plant1.22 kmCaveat
- Industrial zones within 1 km0Caveat
- Nearest airfield runway (any, incl. military)7.03 kmCaveat
- Nearest commercial-airport runway33.86 kmReliable
- Distance to runway approach-path proxy32.51 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat
ReliableFrom our location report at the builder-entered pin (12.88520, 77.65600), 2026-10-24. Each figure's source and caveat are in the full report.