RERA project · Residential/Group Housing
ARYAN GOLDEN ARENA
by Aryan Hometec Pvt Ltd · 72 homes · 0.55 acres · 1 tower · Bengaluru South
Past due, no completion filed Past its deadline of 31 Dec 2021, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Dec 2021, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 52% of the land is left open.
Complaints to RERA about this project. 62 more about the builder's other projects.
The RERA page doesn't say.
Of its 9 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 8 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started20 Jul 2017
- Approved by RERA31 Oct 2017
- First promised31 Mar 2021
The date the builder gave at registration.
- Deadline (extended)31 Dec 2021
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 678 sq ft18 homes63.0 m²
- 654 sq ft9 homes60.8 m²
- 670 sq ft9 homes62.2 m²
- 674 sq ft9 homes62.6 m²
- and 9 homes in other sizes
- 424 sq ft9 homes39.4 m²
- 554 sq ft9 homes51.5 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder listed the areas in sq ft; m² figures are converted.
Towers
Aryan Golden Arena -J: 72 homes, 1 basement
Amenities
- Electricity
- Club House
- Outdoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.55 acres
- Ground covered by buildings
- 48% of the land
2,236 m²
1,068 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 9 RERA projects of ARYAN HOMETEC PVT LTD on the map
Complaints to RERA about its other projects
62 complaints across 9 projects. The most complained about:
- ARYAN GOLDEN ARENA - F 13 complaints
- ARYAN GOLDEN ARENA - G 10 complaints
- ARYAN GOLDEN ARENA - C 9 complaints
- ARYAN FOUNTAIN SQUARE 9 complaints
- ARYAN GOLDEN ARENA - K 7 complaints
Show all 9 projects
- ARYAN GOLDEN ARENA - B 6 complaints
- ARYAN GOLDEN ARENA - E 5 complaints
- ARYAN GOLDEN ARENA - D 2 complaints
- ARYAN FOUNTAIN SQUARE:::PRM/KA/RERA/1251/310/PR/171031/001515 1 complaint
The company
- Registered as
- Aryan Hometec Pvt Ltd
- Type
- Company
- Company number
- U70102KA2007PTC042530
- PAN
- AAGCA6331F
CIN or LLPIN, from the Registrar of Companies.
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/310/PR/171031/001288 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Cancellation of Unit J-507 and Refund of Payments made 19 Dec 2019 · Disposed Ao
- Builder not paying Pre EMIs payment by the builder till possession as commited. 2 Jan 2020 · Disposed Authority Bench6
- Golden Aryan Arena- Pre EMI , cancellation of unit at Golden Arena & reimbursement of paid amount 22 Jan 2020 · Disposed Authority Fullbench
- CANCELATION OF UNIT J-904 AND REFUND OF ENTIRE PAYMENT MADE. 29 Feb 2020 · Disposed Ao
- Refund with Bank interest 30 Jul 2020 · Disposed Authority Bench5
- Refund of booking amount and loan amount processed till date 23 Aug 2020 · Disposed Authority Fullbench
- Refund of Amount - Aryan Hometec 14 Sep 2021 · Disposed Authority Bench6
- Refund of the booking along with Interest paid 8 Apr 2022 · Disposed Authority Bench6
- Delay in the project 20 Sep 2022 · Disposed Authority Bench4
- Complaint under Section 31 of RERA alongwith supporting affidavit. 31 Jan 2023 · Disposed Authority Bench5
- Project Not completed till the time 17 Aug 2023 · Disposed Authority Bench5
- COMPALAINT U/S 31 OF RERA ACT 18 Sep 2024 · Disposed Authority Fullbench
- Application by the allottees to take over of the project 25 Nov 2024 · Disposed Authority Fullbench
- Not Deliverd the flat on the time and work still not started therefore return of money with interest and expenses 7 Jan 2025 · Disposed Authority Fullbench
- ix. It is submitted that the 27 months from 07.09.2017 expired in and around December 2019. However, till date the Respondents have not been able to complete the constructions and hand over the Schedu 15 Mar 2025 · Disposed Authority Fullbench
Documents
45 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹2.5 cr
- Construction
- ₹6.1 cr
- Total project cost
- ₹8.6 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.