Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

ARK OAK TREE

by ARK INFRA DEVELOPERS PRIVATE LIMITED · 176 homes · 2.27 acres · 2 towers · Bengaluru East

Upcoming Under construction, due Feb 2028. 100% built with 75% of the time used. 57% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
100% built

Due 29 Feb 2028. 75% of the time from RERA approval to the deadline has passed.

Built100%
Time used75%
How much is sold?75 left
57% booked

101 of 176 homes, as the builder reported for Q2 2026-27.

How crowded is it?About the same
77 homes per acre

Similar projects within 3 km: 73 per acre. 67% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?2 due so far
0% on time

Of its 3 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 past due with no completion filed, 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Aug 2022
  2. Approved by RERA4 Nov 2022
  3. Today24 Oct 2026

    75% of the time to the deadline has passed.

  4. If it slips like a typical project30 Nov 2028

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2689%
Q4 2025-2697%
Q1 2026-27100%
Q2 2026-27100%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block 1100%
Block 2100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

101 booked75 leftQ2 2026-27

Still available: 41 × 2 BHK, 34 × 3 BHK.

Booked, by type

2 BHK42 of 83
3 BHK59 of 93

Booked, each quarter

Q3 2025-2698 of 176
Q4 2025-26100 of 176
Q1 2026-27101 of 176
Q2 2026-27101 of 176

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
924 sq ft
86 m² carpet · sizes 924–1,217 sq ft (16 at this size)
61 m² land share · 34 m² balcony/terrace · 1 parking space
93 homes · 53% of the project
2 BHK
815 sq ft
76 m² carpet · sizes 737–818 sq ft (25 at this size)
46 m² land share · 29 m² balcony/terrace · 1 parking space
83 homes · 47% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block 19 floors
Block 29 floors

Block 1: 84 homes, 28 m tall, 1 basement · Block 2: 92 homes, 28 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project77
Typical within 3 km (60)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project67%
Typical within 3 km (60)62%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.27 acres

9,206 m²

Ground covered by buildings
33% of the land

3,004 m²

Floor-area ratio
2.25

Floors built per unit of land: 2.25 m² of floors for each m² of land.

Parking
1.14 per home

200 covered, 0 open

Built-up area, all floors
3,40,731 sq ft

31,655 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 3 RERA projects of ARK Infra developers Pvt Ltd on the map

The company

Registered as
ARK INFRA DEVELOPERS PRIVATE LIMITED
Type
Company
PAN
AAICA3369H
GSTIN
29AAICA3369H1ZE

Its other registrations on RERA Karnataka

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹22.3 crBuilding and development ₹38.0 crTotal ₹60.2 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹1.9 cr₹1.9 cr
Q4 2025-26₹4.8 cr₹4.0 cr
Q1 2026-27₹1.8 cr₹1.8 cr
Q2 2026-27₹0.0 lakh₹0.0 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station1.19 kmReliable
  • Nearest railway station1.38 kmReliable
  • Bus stops within 500 m4Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km3Caveat
  • Nearest lake / water body (≥2 ha)2.18 kmCaveat

Hospitals

  • Nearest hospital1.5 kmCaveat

Schools

  • Schools in pincode 560067 (UDISE+ census)57Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km8Caveat
  • Median pupil-teacher ratio, schools within 1 km14.4 :1Caveat
  • Schools with library + playground + ICT lab (1 km)8Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKadugodi PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km18Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)11.42 kmReliable
  • Nearest sewage treatment plant1.93 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)4.85 kmCaveat
  • Nearest commercial-airport runway23.04 kmReliable
  • Distance to runway approach-path proxy21.44 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.98427, 77.76446), 2026-10-24. Each figure's source and caveat are in the full report.