RERA project · Plotted Development
ARATT ROLLING WHITES - PLOTS
by ARATT ROLLING WHITES · 7.76 acres · Anekal
Delivered late Completed: the builder filed for completion on 7 Dec 2019, 308 days after the date it first promised.
At a glance
The builder filed for completion on 7 Dec 2019, 308 days after the date it first promised.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project. 8 more about the builder's other projects.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised).
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started3 Feb 2017
- Approved by RERA14 Dec 2017
- Completion filed7 Dec 2019
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 7.76 acres
- Plot area (the sites)
- 0% of the land
31,388 m²
0 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active plotted development projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of ARATT ROLLING WHITES on the map
Complaints to RERA about its other projects
- ARATT ROLLING WHITES - ROW VILLAS 8 complaints
The company
- Registered as
- ARATT ROLLING WHITES
- Type
- Partnership Firm
- PAN
- ABGFA5088D
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/171214/001755 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Project abandoned by builder without amenities and villa internal work 13 Sep 2022 · Disposed Authority Bench4
- Pending and Unfinished Amenities 23 Nov 2023 · Disposed Authority
Documents
44 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹7.6 cr
- Construction
- ₹8.3 cr
- Total project cost
- ₹15.9 cr
CaveatCost as certified by the builder's chartered accountant at registration.