RERA project · Residential/Group Housing
ARATT CITYSCAPES
by ARATT CITYSCAPES PROJECT LLP · 363 homes · 10.35 acres · 7 towers · Bengaluru East
Past due, no completion filed Past its deadline of 30 Sep 2024, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 30 Sep 2024, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects across the city: 76 per acre. 58% of the land is left open.
Complaints to RERA about this project.
The RERA page doesn't say.
It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started1 Jul 2017
- Approved by RERA22 Dec 2017
- First promised30 Jun 2022
The date the builder gave at registration.
- Deadline (extended)30 Sep 2024
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
- 2,435 sq ft27 homes226.2 m²
- 2,058 sq ft26 homes191.2 m²
- 1,896 sq ft16 homes176.1 m²
- 2,421 sq ft16 homes224.9 m²
- and 126 homes in other sizes
- 1,194 sq ft72 homes110.9 m²
- 1,228 sq ft40 homes114.1 m²
- 1,082 sq ft40 homes100.5 m²
Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Ferndale: 56 homes · Mayflower: 48 homes · Arcadia: 42 homes, 1 basement · Ashton: 45 homes, 1 basement · Lilac: 52 homes, 1 basement · Willow: 72 homes, 1 basement · Palmgroove: 48 homes
Amenities
- Electricity
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 10.35 acres
- Ground covered by buildings
- 42% of the land
41,881 m²
17,717 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.
The company
- Registered as
- ARATT CITYSCAPES PROJECT LLP
- Type
- Other
- PAN
- ABFFA2759N
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/171222/001233 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Not refunding the agreement and booking amount after cancelling the booking against unit B-401 in ARATT CITYSCAPES-MAY FLOWER 8 Sep 2021 · Disposed Authority Bench5
- Delay in the project 21 Oct 2023 · Disposed Authority Bench4
- Delay interest and compensation 25 Mar 2024 · Disposed Authority Fullbench
- Complaint Regarding Delay in Property Handover - but cancellation notice sent, builder harassment 17 Feb 2025 · Posted For Orders Authority Fullbench
- Behavorial/Mental Harassment & Undue influence to consider there associate bank to earn mediator commission 2 Apr 2025 · Disposed Authority Fullbench
Documents
60 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹12.2 cr
- Construction
- ₹114.5 cr
- Total project cost
- ₹126.8 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.