Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

Aparna Maple

by Aparna Constructions And Estates Pvt Ltd · 246 homes · 3.32 acres · 2 towers · Bengaluru East

Delivered late Completed: the builder filed for completion on 29 May 2024, 167 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 29 May 2024, 167 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?About the same
74 homes per acre

Similar projects within 3 km: 73 per acre. 81% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?1 due so far
0% on time

Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 1 late (after the date first promised), 1 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started17 Jan 2019
  2. Approved by RERA24 Jul 2019
  3. First promised14 Dec 2023

    The date the builder gave at registration.

  4. Completion filed29 May 2024

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2BHK
720 sq ft
67 m² carpet · sizes 512–721 sq ft (60 at this size)
512 m² land share · 179 m² balcony/terrace · 1 parking space
124 homes · 50% of the project
3BHK
888 sq ft
82 m² carpet · sizes 700–1,011 sq ft (62 at this size)
618 m² land share · 197 m² balcony/terrace · 2 parking spaces
122 homes · 50% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

T1-Block- 114 floors
T2-Block-215 floors

T1-Block- 1: 119 homes, 2 basements · T2-Block-2: 127 homes, 2 basements

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project74
Typical within 3 km (120)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project81%
Typical within 3 km (120)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
3.32 acres

13,434 m²

Ground covered by buildings
19% of the land

2,563 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 2 RERA projects of Aparna Constructions And Estates Pvt Ltd on the map

The company

Registered as
Aparna Constructions And Estates Pvt Ltd
Type
Company
PAN
AADCA1031D

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹39.8 cr
Construction
₹107.8 cr
Total project cost
₹147.6 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station8.47 kmReliable
  • Nearest railway station6.46 kmReliable
  • Bus stops within 500 m5Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km9Caveat
  • Nearest lake / water body (≥2 ha)0.91 kmCaveat

Hospitals

  • Nearest hospital0.12 kmCaveat

Schools

  • Schools in pincode 560077 (UDISE+ census)123Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km9Caveat
  • Median pupil-teacher ratio, schools within 1 km23.7 :1Caveat
  • Schools with library + playground + ICT lab (1 km)4Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKothanur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)3.94 kmReliable
  • Nearest sewage treatment plant2.66 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)4.32 kmCaveat
  • Nearest commercial-airport runway14.53 kmReliable
  • Distance to runway approach-path proxy12.26 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (13.06779, 77.63992), 2026-10-24. Each figure's source and caveat are in the full report.