Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

AKIRA APARTMENT (NANJUNDESHWARA ENCLAVE)

by S V CONSULTANTS AND ENGINEERS · 18 homes · 0.21 acres · 1 tower · Bengaluru North

Past due, no completion filed Past its deadline of 31 Dec 2020, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 31 Dec 2020, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?Less crowded
85 homes per acre

Similar projects within 3 km: 106 per acre. 40% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started3 Sep 2018
  2. Approved by RERA28 Mar 2019
  3. First promised31 Mar 2020

    The date the builder gave at registration.

  4. Deadline (extended)31 Dec 2020

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2BHK
494 sq ft
46 m² carpet · sizes 494–690 sq ft (3 at this size)
47 m² land share · 6 m² balcony/terrace · 1 parking space
18 homes · 100% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Akira2 floors

Akira: 18 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project85
Typical within 3 km (10)106
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project40%
Typical within 3 km (10)65%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.21 acres

854 m²

Ground covered by buildings
60% of the land

512 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
S V CONSULTANTS AND ENGINEERS
Type
Partnership Firm
PAN
ABNFS4341N

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹4.5 cr
Construction
₹3.4 cr
Total project cost
₹7.9 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station4.63 kmReliable
  • Nearest railway station3.09 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)1.39 kmCaveat

Hospitals

  • Nearest hospital1.66 kmCaveat

Schools

  • Schools in pincode 560074 (UDISE+ census)70Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionTavarekere PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km1Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)18.77 kmReliable
  • Nearest sewage treatment plant3.1 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)26.16 kmCaveat
  • Nearest commercial-airport runway45.09 kmReliable
  • Distance to runway approach-path proxy39.22 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (12.87562, 77.42477), 2026-10-24. Each figure's source and caveat are in the full report.