Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

AFTER THE RAIN-PHASE IIC

by Total Environment Building Systems Private limited · 26 homes · 4.37 acres · 6 towers · Bengaluru North

Upcoming Under construction, due Apr 2028. 48% built with 76% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
48% built

Due 1 Apr 2028. 76% of the time from RERA approval to the deadline has passed.

Built48%
Time used76%
How much is sold?0 left
100% booked

26 of 26 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
6 homes per acre

Similar projects within 3 km: 30 per acre. 35% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 3 more about the builder's other projects.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?9 due so far
11% on time

Of its 22 RERA projects in Bengaluru Urban: 1 delivered on time, 5 late (after the date first promised), 3 past due with no completion filed, 13 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA30 Mar 2022
  2. Work started1 Apr 2022
  3. Today24 Oct 2026

    76% of the time to the deadline has passed.

  4. If it slips like a typical project1 Jan 2029

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2668%
Q4 2025-2649%
Q1 2026-2748%
Q2 2026-2748%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block 0631%
Block 1932%
Block 2061%
Block 2832%
Block 2932%
Block 3032%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

26 booked0 leftQ2 2026-27

Booked, by type

4 BHK26 of 26

Booked, each quarter

Q3 2025-2624 of 26
Q4 2025-2624 of 26
Q1 2026-2724 of 26
Q2 2026-2726 of 26

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

4 BHK
  • 4,058 sq ft16 homes377.0 m²
  • 2,702 sq ft10 homes251.0 m²
Typically 420 m² land share · 207 m² balcony/terrace · 2 parking spaces
26 homes · 100% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Block 061 floor
Block 191 floor
Block 201 floor
Block 281 floor
Block 291 floor
Block 301 floor

Block 06: 12 homes, 9 m tall, 12 basements · Block 19: 2 homes, 9 m tall, 2 basements · Block 20: 2 homes, 9 m tall, 2 basements · Block 28: 4 homes, 8 m tall · Block 29: 4 homes, 8 m tall · Block 30: 2 homes, 8 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project6
Typical within 3 km (10)30
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project35%
Typical within 3 km (10)76%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.37 acres

17,700 m²

Ground covered by buildings
65% of the land

11,513 m²

Floor-area ratio
0.52

Floors built per unit of land: 0.52 m² of floors for each m² of land.

Parking
2.19 per home

52 covered, 5 open

Built-up area, all floors
1,44,344 sq ft

13,410 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 22 RERA projects of Total Environment on the map

Complaints to RERA about its other projects

The company

Registered as
Total Environment Building Systems Private limited
Type
Company
Company number
U45202KA1996PTC020790

CIN or LLPIN, from the Registrar of Companies.

PAN
AABCT9452T
GSTIN
29AABCT9452F1Z2
Website
https://www.total-environment.com/

Its other registrations on RERA Karnataka

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹13.3 crBuilding and development ₹108.8 crTotal ₹122.1 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹21.7 lakh₹18.2 lakh
Q4 2025-26₹21.7 lakh₹3.5 cr
Q1 2026-27₹2.5 cr₹2.5 cr
Q2 2026-27₹44.9 lakh₹44.9 lakh

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station15.82 kmReliable
  • Nearest railway station4.35 kmReliable
  • Bus stops within 500 m1Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.72 kmCaveat

Hospitals

  • Nearest hospital1.19 kmCaveat

Schools

  • Schools in pincode 562157 (UDISE+ census)56Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionChikkajala PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km14Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)7.24 kmReliable
  • Nearest sewage treatment plant3.91 kmCaveat
  • Industrial zones within 1 km2Caveat
  • Nearest airfield runway (any, incl. military)2.56 kmCaveat
  • Nearest commercial-airport runway10.09 kmReliable
  • Distance to runway approach-path proxy2.46 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)0Caveat

ReliableFrom our location report at the builder-entered pin (13.15902, 77.60240), 2026-10-24. Each figure's source and caveat are in the full report.