RERA project · Residential/Group Housing
Affinity Serenity
by Sudhakara Reddy Annem · 0.21 acres · Bengaluru North
Past due, no completion filed Past its deadline of 1 Feb 2022, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 1 Feb 2022, and no completion is filed.
The builder has not filed bookings on RERA.
The RERA page gives no usable land area.
Complaints to RERA about this project.
The RERA page doesn't say.
Of its 2 RERA projects in Bengaluru Urban: 0 delivered on time, 2 past due with no completion filed.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Work started10 Feb 2019
- Approved by RERA23 Aug 2019
- First promised1 May 2021
The date the builder gave at registration.
- Deadline (extended)1 Feb 2022
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How crowded is it?
Land left open
The share of the land not built on, which includes roads.
- Land
- 0.21 acres
- Ground covered by buildings
- 54% of the land
836 m²
454 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 2 RERA projects of Sudhakara Reddy Annem on the map
The company
- Registered as
- Sudhakara Reddy Annem
- Type
- Partnership Firm
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/309/PR/190823/002807 · Approved
- Building plan approvedBBMP - Bruhat Bengaluru Mahanagara Palike
- Litigation on the landNot stated
- Litigation on the projectNot stated
Complaints to RERA about this project
- Delivery date expiry 17 Nov 2022 · Disposed Authority Bench6
- Compensation 17 Nov 2022 · Disposed Ao
Documents
41 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
- Land
- ₹4.0 cr
- Construction
- ₹4.0 cr
- Total project cost
- ₹8.0 cr
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
This project lists no location on RERA, so there is no location report for it.