by Varin Infra Projects Private Limited · 201 homes · 4.12 acres · 10 towers · Bengaluru East

Past due, no completion filed Past its deadline of 6 Mar 2026, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 6 Mar 2026, and no completion is filed.

How much is sold?59 left
71% booked

142 of 201 homes, as the builder reported for Q4 2025-26.

How crowded is it?Less crowded
49 homes per acre

Similar projects within 3 km: 74 per acre. 62% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 5 more about the builder's other projects.

Any legal cases?Litigation
Declared

The builder declares litigation on the land or the project.

What is the builder's record?20 due so far
0% on time

Of its 41 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 18 past due with no completion filed, 20 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jun 2018
  2. Approved by RERA10 Dec 2018
  3. First promised28 Feb 2022

    The date the builder gave at registration.

  4. Deadline (extended)6 Mar 2026

    Passed with no completion filed.

How much is built, each quarter

Q3 2025-2698%
Q4 2025-2698%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q4 2025-26

A100%
B100%
C100%
D100%
E100%
F100%
G100%
H100%
J100%
K100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

142 booked59 leftQ4 2025-26

Still available: 10 × 2.5BHK, 12 × 2BHK, 37 × 3BHK.

Booked, by type

2.5BHK50 of 60
2BHK23 of 35
3BHK66 of 103
1.5BHK3 of 3

Booked, each quarter

Q3 2025-26162 of 201
Q4 2025-26142 of 201

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3BHK
1,163 sq ft
108 m² carpet · sizes 1,119–1,238 sq ft (40 at this size)
1 parking space
103 homes · 51% of the project
2.5BHK
1,012 sq ft
94 m² carpet · sizes 1,001–1,087 sq ft (14 at this size)
1 parking space
60 homes · 30% of the project
2BHK
818 sq ft
76 m² carpet · sizes 807–936 sq ft (14 at this size)
1 parking space
35 homes · 17% of the project
1.5BHK
732 sq ft
68 m² carpet · sizes 732–775 sq ft (1 at this size)
1 parking space
3 homes · 1% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

A4 floors
B4 floors
C4 floors
D4 floors
E4 floors
F4 floors
G4 floors
H4 floors
J4 floors
K4 floors

A: 20 homes, 1 basement · B: 20 homes, 1 basement · C: 20 homes, 1 basement · D: 23 homes, 1 basement · E: 20 homes, 1 basement · F: 20 homes, 1 basement · G: 20 homes, 1 basement · H: 18 homes, 1 basement · J: 20 homes, 1 basement · K: 20 homes, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project49
Typical within 3 km (65)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project62%
Typical within 3 km (67)56%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
4.12 acres

16,693 m²

Ground covered by buildings
38% of the land

6,387 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 41 RERA projects of Adarsh Developers on the map

Complaints to RERA about its other projects

The company

Registered as
Varin Infra Projects Private Limited
Type
Company
Company number
U45200KA2011PTC059980

CIN or LLPIN, from the Registrar of Companies.

PAN
AADCV7467N

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹1.5 cr
Construction
₹135.2 cr
Total project cost
₹136.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹140.3 cr₹175.9 cr
Q4 2025-26₹142.6 cr₹175.9 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station9.06 kmReliable
  • Nearest railway station7.54 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km1Caveat
  • Nearest lake / water body (≥2 ha)1.01 kmCaveat

Hospitals

  • Nearest hospital2.33 kmCaveat

Schools

  • Schools in pincode 560077 (UDISE+ census)123Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km6Caveat
  • Median pupil-teacher ratio, schools within 1 km11.8 :1Caveat
  • Schools with library + playground + ICT lab (1 km)4Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionKothanur PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km2Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)2.92 kmReliable
  • Nearest sewage treatment plant3.97 kmCaveat
  • Industrial zones within 1 km4Caveat
  • Nearest airfield runway (any, incl. military)6.36 kmCaveat
  • Nearest commercial-airport runway12.55 kmReliable
  • Distance to runway approach-path proxy11.17 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)0Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat

ReliableFrom our location report at the builder-entered pin (13.08000, 77.66000), 2026-10-24. Each figure's source and caveat are in the full report.