Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

ADARSH GREENS PHASE 1

by ADARSH HAVEN PRIVATE LIMITED · 669 homes · 6.59 acres · 3 towers · Bengaluru North

Upcoming Under construction, due Oct 2026, after an extension. 99% built with 100% of the time used. 100% of homes booked.

Location report

At a glance

Is it on schedule?Deadline extended
99% built

Due 31 Oct 2026. 100% of the time from RERA approval to the deadline has passed.

Built99%
Time used100%
How much is sold?0 left
100% booked

669 of 669 homes, as the builder reported for Q2 2026-27.

How crowded is it?More crowded
102 homes per acre

Similar projects within 3 km: 73 per acre. 82% of the land is left open.

Any complaints?See the list
12 complaints

Complaints to RERA about this project. 25 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?20 due so far
0% on time

Of its 41 RERA projects in Bengaluru Urban: 0 delivered on time, 2 late (after the date first promised), 18 past due with no completion filed, 20 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Approved by RERA1 Oct 2020
  2. Work started14 Oct 2020
  3. First promised31 Oct 2024

    The date the builder gave at registration.

  4. Today24 Oct 2026

    100% of the time to the deadline has passed.

  5. If it slips like a typical project2 Aug 2027

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q3 2025-2699%
Q4 2025-2699%
Q1 2026-2799%
Q2 2026-2799%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

By tower, Q2 2026-27

Block A100%
Block G100%
Block H100%

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

669 booked0 leftQ2 2026-27

Booked, by type

2BHK566 of 566
1BHK103 of 103

Booked, each quarter

Q3 2025-26669 of 669
Q4 2025-26669 of 669
Q1 2026-27669 of 669
Q2 2026-27669 of 669

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

2BHK
642 sq ft
60 m² carpet · sizes 630–642 sq ft (296 at this size)
28 m² land share · 1 parking space
566 homes · 85% of the project
1BHK
421 sq ft
39 m² carpet
18 m² land share · 1 parking space
103 homes · 15% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home. The builder gave these areas in sq ft; m² figures are converted.

Towers

Block A13 floors
Block G13 floors
Block H13 floors

Block A: 193 homes, 1 basement · Block G: 309 homes, 1 basement · Block H: 167 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project102
Typical within 3 km (89)73
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project82%
Typical within 3 km (90)60%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
6.59 acres

26,676 m²

Ground covered by buildings
18% of the land

4,824 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 41 RERA projects of Adarsh Developers on the map

Complaints to RERA about its other projects

The company

Registered as
ADARSH HAVEN PRIVATE LIMITED
Type
Other
Company number
U45202KA2009PTC051266

CIN or LLPIN, from the Registrar of Companies.

PAN
AAICA0192Q

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹28.5 cr
Construction
₹226.4 cr
Total project cost
₹255.0 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q3 2025-26₹245.5 cr₹248.3 cr
Q4 2025-26₹247.2 cr₹226.4 cr
Q1 2026-27₹247.2 cr₹226.4 cr
Q2 2026-27₹247.8 cr₹248.3 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station10.5 kmReliable
  • Nearest railway station2.4 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km0Caveat
  • Parks within 1 km0Caveat
  • Nearest lake / water body (≥2 ha)0.91 kmCaveat

Hospitals

  • Nearest hospital1.42 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionSampigehalli PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well16.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km10Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)3.81 kmReliable
  • Nearest sewage treatment plant0.66 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)2.35 kmCaveat
  • Nearest commercial-airport runway13.36 kmReliable
  • Distance to runway approach-path proxy8.93 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (13.09608, 77.61204), 2026-10-24. Each figure's source and caveat are in the full report.