RERA project · Residential/Group Housing
ABHEE PRIDE
by ABHEE VENTURES PRIVATE LIMITED · 104 homes · 1.26 acres · 1 tower · Anekal
Delivered late Completed: the builder filed for completion on 6 Aug 2026, 37 days after the date it first promised.
At a glance
The builder filed for completion on 6 Aug 2026, 37 days after the date it first promised.
101 of 104 homes, as the builder reported for Q1 2026-27.
Similar projects within 3 km: 78 per acre. 73% of the land is left open.
Complaints to RERA about this project. 1 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 10 RERA projects in Bengaluru Urban: 0 delivered on time, 4 late (after the date first promised), 1 past due with no completion filed, 5 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
Was it delivered on time?
- Work started2 Jan 2023
- Approved by RERA22 Feb 2023
- Completion filed6 Aug 2026
The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Still available: 2 × 2 BHK, 1 × 2.5 BHK.
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Abhee Pride: 104 homes, 27 m tall, 1 basement
Amenities
- Electricity 3,735 m²
- CCTV Surveillance 1,360 m²
- Community Hall 160 m²
- Outdoor Sports facility 80 m²
- Indoor Sports facility 30 m²
- Swimming Pool 84 m²
- Gym 60 m²
- Power Backup 1,360 m²
- Water and Sanitation 5,095 m²
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 1.26 acres
- Ground covered by buildings
- 27% of the land
- Floor-area ratio
- 2.00
- Parking
- 1.11 per home
- Built-up area, all floors
- 1,62,330 sq ft
5,095 m²
1,361 m²
Floors built per unit of land: 2.00 m² of floors for each m² of land.
115 covered, 0 open
15,081 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 10 RERA projects of ABHEE VENTURES PRIVATE LIMITED on the map
Complaints to RERA about its other projects
- ABHEE AARIA 1 complaint
The company
- Registered as
- ABHEE VENTURES PRIVATE LIMITED
- Type
- Company
- Company number
- U45203KA2021PTC153091
- PAN
- AAVCA9517E
- GSTIN
- 29AAVCA9517E1Z5
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
9 registrations under this company
- ABHEE CITY URBAN GLENN PHASE II PRM/KA/RERA/1251/308/PR/300926/008986 · approved 30 Sep 2026
- ABHEE CITY URBAN GLENN PHASE I PRM/KA/RERA/1251/308/PR/250826/008887 · approved 25 Aug 2026
- ABHEE TRANQUILA PRM/KA/RERA/1251/310/PR/020725/007891 · approved 2 Jul 2025
- ABHEE SERENITY SPRINGS PRM/KA/RERA/1251/308/PR/180325/007592 · approved 18 Mar 2025
- ABHEE AARIA PRM/KA/RERA/1251/309/PR/050325/007545 · approved 5 Mar 2025
- ABHEE RIVIERA ROYALE PRM/KA/RERA/1251/310/PR/210324/006722 · approved 21 Mar 2024
- ABHEE KINGS COURT PRM/KA/RERA/1251/308/PR/020323/005763 · approved 2 Mar 2023
- ABHEE SRISHTI LAYOUT PRM/KA/RERA/1251/308/PR/080223/005701 · approved 8 Feb 2023
- ABHEE NANDANA BLOCK-C PRM/KA/RERA/1251/446/PR/310522/004944 · approved 31 May 2022
The land is owned together with others (a joint development).
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/308/PR/220223/005739 · Approved
- Building plan approvedBMRDA - Bangalore Metropolitan Region Development Authority · APA/CC/131/2022-23 · 3 Dec 2022
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q1 2026-27 update
- Water sourceBoreWell
Complaints to RERA about this project
None on RERA Karnataka.
Documents
168 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹4.3 cr | ₹1.5 cr |
| Q4 2025-26 | ₹17.3 lakh | ₹0.0 lakh |
| Q1 2026-27 | ₹11.6 lakh | ₹0.0 lakh |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station3.95 kmReliable
- Nearest railway station3.52 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km4Caveat
- Nearest lake / water body (≥2 ha)0.78 kmCaveat
Hospitals
- Nearest hospital1.53 kmCaveat
Schools
- Schools in pincode 560081 (UDISE+ census)12Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionAttibele PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)9.43 kmReliable
- Nearest sewage treatment plant1.03 kmCaveat
- Industrial zones within 1 km4Caveat
- Nearest airfield runway (any, incl. military)18.49 kmCaveat
- Nearest commercial-airport runway44.77 kmReliable
- Distance to runway approach-path proxy44.06 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)1Caveat
ReliableFrom our location report at the builder-entered pin (12.78466, 77.69694), 2026-10-24. Each figure's source and caveat are in the full report.