Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

ABHEE NANDANA BLOCK-C

by ABHEE VENTURES PRIVATE LIMITED · 16 homes · 0.17 acres · 1 tower · Bengaluru East

Delivered late Completed: the builder filed for completion on 12 Jan 2024, 12 days after the date it first promised.

Location report

At a glance

Was it on time?Delivered late
Completed late

The builder filed for completion on 12 Jan 2024, 12 days after the date it first promised.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
92 homes per acre

Similar projects within 3 km: 68 per acre. 52% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 1 more about the builder's other projects.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?5 due so far
0% on time

Of its 10 RERA projects in Bengaluru Urban: 0 delivered on time, 4 late (after the date first promised), 1 past due with no completion filed, 5 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

Was it delivered on time?

  1. Work started1 May 2021
  2. Approved by RERA31 May 2022
  3. Completion filed12 Jan 2024

    The builder told RERA the project is complete. Ask for the occupancy certificate before moving in.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

2 BHK
380 sq ft
35 m² carpet · sizes 380–545 sq ft (4 at this size)
38 m² land share · 1 parking space
8 homes · 50% of the project
3 BHK
724 sq ft
67 m² carpet · sizes 724–885 sq ft (4 at this size)
51 m² land share · 1 parking space
8 homes · 50% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower C3 floors

Tower C: 16 homes, 15 m tall

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project92
Typical within 3 km (81)68
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project52%
Typical within 3 km (81)58%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
0.17 acres

708 m²

Ground covered by buildings
48% of the land

342 m²

Floor-area ratio
1.75

Floors built per unit of land: 1.75 m² of floors for each m² of land.

Parking
1.00 per home

0 covered, 16 open

Built-up area, all floors
14,273 sq ft

1,326 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 10 RERA projects of ABHEE VENTURES PRIVATE LIMITED on the map

Complaints to RERA about its other projects

The company

Registered as
ABHEE VENTURES PRIVATE LIMITED
Type
Company
Company number
U45203KA2021PTC153091

CIN or LLPIN, from the Registrar of Companies.

PAN
AAVCA9517E

Its other registrations on RERA Karnataka

9 registrations under this company
  • ABHEE CITY URBAN GLENN PHASE II PRM/KA/RERA/1251/308/PR/300926/008986 · approved 30 Sep 2026
  • ABHEE CITY URBAN GLENN PHASE I PRM/KA/RERA/1251/308/PR/250826/008887 · approved 25 Aug 2026
  • ABHEE TRANQUILA PRM/KA/RERA/1251/310/PR/020725/007891 · approved 2 Jul 2025
  • ABHEE SERENITY SPRINGS PRM/KA/RERA/1251/308/PR/180325/007592 · approved 18 Mar 2025
  • ABHEE AARIA PRM/KA/RERA/1251/309/PR/050325/007545 · approved 5 Mar 2025
  • ABHEE RIVIERA ROYALE PRM/KA/RERA/1251/310/PR/210324/006722 · approved 21 Mar 2024
  • ABHEE KINGS COURT PRM/KA/RERA/1251/308/PR/020323/005763 · approved 2 Mar 2023
  • ABHEE PRIDE PRM/KA/RERA/1251/308/PR/220223/005739 · approved 22 Feb 2023
  • ABHEE SRISHTI LAYOUT PRM/KA/RERA/1251/308/PR/080223/005701 · approved 8 Feb 2023

The land is owned together with others (a joint development), including Abhee Developers.

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹2.3 crBuilding and development ₹4.4 crTotal ₹6.7 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station2.85 kmReliable
  • Nearest railway station4.74 kmReliable
  • Bus stops within 500 m0Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km15Caveat
  • Nearest lake / water body (≥2 ha)0.56 kmCaveat

Hospitals

  • Nearest hospital0.8 kmCaveat

Schools

  • Schools in pincode 560102 (UDISE+ census)38Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km3Caveat
  • Schools with library + playground + ICT lab (1 km)3Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionBellanduru PSReliable

Air quality

  • PM2.5, recent 24 h avg (nearest CPCB station)18 µg/m³Caveat

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km0Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • In an IISc groundwater-critical ward (2025 outlook)noCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km0Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)1.65 kmReliable
  • Nearest sewage treatment plant2.16 kmCaveat
  • Industrial zones within 1 km0Caveat
  • Nearest airfield runway (any, incl. military)5.24 kmCaveat
  • Nearest commercial-airport runway31.95 kmReliable
  • Distance to runway approach-path proxy30.75 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)2Caveat

ReliableFrom our location report at the builder-entered pin (12.90195, 77.66246), 2026-10-24. Each figure's source and caveat are in the full report.