Past due, no completion filed Past its deadline of 31 Jul 2025, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.
At a glance
The deadline was 31 Jul 2025, and no completion is filed.
The builder has not filed bookings on RERA.
Similar projects within 3 km: 68 per acre. 91% of the land is left open.
Complaints to RERA about this project. 4 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Approved by RERA24 Jan 2022
- Work started1 Feb 2022
- Deadline31 Jul 2025
Passed with no completion filed.
No quarterly construction update is filed on this project's RERA page.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
63 Degree East - Tower F: 88 homes, 45 m tall, 1 basement
Amenities
- Electricity 21 m²
- CCTV Surveillance
- Club House 3,001 m²
- Outdoor Sports facility
- Indoor Sports facility 865 m²
- Swimming Pool 536 m²
- Gym 190 m²
- Parks 10,691 m²
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 2.52 acres
- Ground covered by buildings
- 9% of the land
- Floor-area ratio
- 0.13
- Parking
- 1.52 per home
- Built-up area, all floors
- 1,76,980 sq ft
10,198 m²
878 m²
Floors built per unit of land: 0.13 m² of floors for each m² of land.
114 covered, 20 open
16,442 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 54 RERA projects of Assetz on the map
Complaints to RERA about its other projects
- 63 Degree East - Tower E 2 complaints
- 63 Degree East - Tower C & D 1 complaint
- Leaves & Lives Phase 1 1 complaint
The company
- Registered as
- APG Intelli Homes Private Limited
- Type
- Company
- Company number
- U70100KA2014PTC077189
- PAN
- AANCA0060C
- GSTIN
- 29AANCA0060C1Z1
- Website
- www.assetzproperty.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
6 registrations under this company
- 63 Degree East - Tower E PRM/KA/RERA/1251/446/PR/201222/005546 · approved 20 Dec 2022
- 63 Degree East - Tower A PRM/KA/RERA/1251/446/PR/240122/004656 · approved 24 Jan 2022
- Leaves & Lives Phase 2 PRM/KA/RERA/1251/446/PR/210928/004328 · approved 28 Sep 2021
- 63 degree east - Tower B PRM/KA/RERA/1251/446/PR/190504/002547 · approved 4 May 2019
- Leaves & Lives Phase 1 PRM/KA/RERA/1251/446/PR/180808/001979 · approved 8 Aug 2018
- 63 Degree East - Tower C & D PRM/KA/RERA/1251/446/PR/171030/000980 · approved 30 Oct 2017
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/240122/004655 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/LP/EM/EO-03/TA-2/S/06/2021-22 · 8 Dec 2021
- Litigation on the landNone declared
- Litigation on the projectNot stated
- Water sourceLocal Authority
Complaints to RERA about this project
None on RERA Karnataka.
Documents
151 files on the RERA page: Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station5.46 kmReliable
- Nearest railway station2.35 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km5Caveat
- Nearest lake / water body (≥2 ha)0.54 kmCaveat
Hospitals
- Nearest hospital1.48 kmCaveat
Schools
- Schools in pincode 560035 (UDISE+ census)45Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)3Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionBellanduru PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)6.07 kmReliable
- Nearest sewage treatment plant3.13 kmCaveat
- Industrial zones within 1 km2Caveat
- Nearest airfield runway (any, incl. military)7.52 kmCaveat
- Nearest commercial-airport runway33.53 kmReliable
- Distance to runway approach-path proxy33 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat
ReliableFrom our location report at the builder-entered pin (12.88620, 77.70380), 2026-10-24. Each figure's source and caveat are in the full report.