RERA project · Residential/Group Housing
63 Degree East - Tower E
by APG Intelli Homes Private Limited · 399 homes · 5.36 acres · 1 tower · Bengaluru East
Upcoming Under construction, due Dec 2026. 92% built with 95% of the time used. 100% of homes booked.
At a glance
Due 31 Dec 2026. 95% of the time from RERA approval to the deadline has passed.
399 of 399 homes, as the builder reported for Q2 2026-27.
Similar projects within 3 km: 68 per acre. 78% of the land is left open.
Complaints to RERA about this project. 2 more about the builder's other projects.
No litigation on the land or the project, as the builder declares it to RERA.
Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.
These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.
When will it be ready?
- Approved by RERA20 Dec 2022
- Work started1 Jan 2023
- Today24 Oct 2026
95% of the time to the deadline has passed.
- Deadline31 Dec 2026
The date it must be complete by.
- If it slips like a typical project2 Oct 2027
35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.
How much is built, each quarter
Built, as the builder reports itTime used by then
When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.
CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.
How much is sold?
Booked, by type
Booked, each quarter
Booked means sold or reserved, as the builder reports it. It says nothing about prices.
CaveatFrom the builder's quarterly updates to RERA Karnataka.
What's being built?
Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.
Towers
Tower -E: 399 homes, 60 m tall, 1 basement
Amenities
- Electricity 210 m²
- CCTV Surveillance
- Club House 3,001 m²
- Outdoor Sports facility 4,153 m²
- Indoor Sports facility 865 m²
- Swimming Pool 536 m²
- Gym 190 m²
- Parks 10,691 m²
- Power Backup
- Water and Sanitation
CaveatAs registered by the builder on RERA Karnataka.
How crowded is it?
Homes per acre
Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.
Land left open
The share of the land not built on, which includes roads.
- Land
- 5.36 acres
- Ground covered by buildings
- 23% of the land
- Floor-area ratio
- 0.52
- Parking
- 1.19 per home
- Built-up area, all floors
- 7,23,216 sq ft
21,681 m²
4,884 m²
Floors built per unit of land: 0.52 m² of floors for each m² of land.
441 covered, 33 open
67,189 m²
CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.
Who is building it?
All 54 RERA projects of Assetz on the map
Complaints to RERA about its other projects
- 63 Degree East - Tower C & D 1 complaint
- Leaves & Lives Phase 1 1 complaint
The company
- Registered as
- APG Intelli Homes Private Limited
- Type
- Company
- Company number
- U70100KA2014PTC077189
- PAN
- AANCA0060C
- GSTIN
- 29AANCA0060C1Z1
- Website
- www.assetzproperty.com
CIN or LLPIN, from the Registrar of Companies.
Its other registrations on RERA Karnataka
6 registrations under this company
- 63 Degree East - Tower A PRM/KA/RERA/1251/446/PR/240122/004656 · approved 24 Jan 2022
- 63 Degree East - Tower F PRM/KA/RERA/1251/446/PR/240122/004655 · approved 24 Jan 2022
- Leaves & Lives Phase 2 PRM/KA/RERA/1251/446/PR/210928/004328 · approved 28 Sep 2021
- 63 degree east - Tower B PRM/KA/RERA/1251/446/PR/190504/002547 · approved 4 May 2019
- Leaves & Lives Phase 1 PRM/KA/RERA/1251/446/PR/180808/001979 · approved 8 Aug 2018
- 63 Degree East - Tower C & D PRM/KA/RERA/1251/446/PR/171030/000980 · approved 30 Oct 2017
CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.
Paperwork and legal
- Registered with RERAPRM/KA/RERA/1251/446/PR/201222/005546 · Approved
- Building plan approvedBDA - Bangalore Development Authority · BDA/LP/EM/EO-3/TA-2/E/33/2022-23 · 25 Nov 2022
- Litigation on the landNone declared
- Litigation on the projectNone declared in the Q2 2026-27 update
- Water sourceLocal Authority
Complaints to RERA about this project
- Misrepresentation and suppression of material facts by the Respondent in failing to disclose the EWS status of Flats E-3194, E-3195 and E-3196 to the Complainants at the time of sale 3 Jul 2026 · Under Enquiry Authority Bench6
- Structural Alteration / Deviation from Sanctioned Plan and Enforce Three different Sales Deed 21 Jul 2026 · Posted For Orders Authority Fullbench
Documents
181 files on the RERA page: Approved plan ↗, Commencement certificate ↗, Brochure ↗.
CaveatAs filed on RERA Karnataka. Complaints are listed without the names of the people who filed them.
Project cost
Money from buyers, each quarter
| Quarter | Collected from buyers | Withdrawn from the project account |
|---|---|---|
| Q3 2025-26 | ₹0.0 lakh | ₹0.0 lakh |
| Q4 2025-26 | ₹5.0 cr | ₹3.3 cr |
| Q1 2026-27 | ₹8.0 cr | ₹5.3 cr |
| Q2 2026-27 | ₹9.6 cr | ₹6.4 cr |
Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.
CaveatCost as certified by the builder's chartered accountant at registration.
What's around it?
Open the full location report on the map
Metro, rail, bus, airport
- Nearest operational metro station5.46 kmReliable
- Nearest railway station2.36 kmReliable
- Bus stops within 500 m0Caveat
Parks, shops, daily needs
- Supermarkets within 1 km0Caveat
- Parks within 1 km5Caveat
- Nearest lake / water body (≥2 ha)0.55 kmCaveat
Hospitals
- Nearest hospital1.49 kmCaveat
Schools
- Schools in pincode 560035 (UDISE+ census)45Caveat
- Private (classes 1–10 or 1–12), government and central schools within 1 km4Caveat
- Schools with library + playground + ICT lab (1 km)3Caveat
Police and crime
- Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
- Police station jurisdictionBellanduru PSReliable
Flood and waterlogging
- BBMP-listed flood / low-lying spots within 1 km0Caveat
Water availability
- Groundwater stage (CGWB block assessment)Over ExploitedCaveat
Power reliability
- Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
- Un/partially-electrified layouts within 1 km0Caveat
Landfills, sewage plants, industry, aircraft
- Nearest named landfill / dump site (≥2 ha)6.07 kmReliable
- Nearest sewage treatment plant3.12 kmCaveat
- Industrial zones within 1 km2Caveat
- Nearest airfield runway (any, incl. military)7.53 kmCaveat
- Nearest commercial-airport runway33.54 kmReliable
- Distance to runway approach-path proxy33.01 kmCaveat
Upcoming infrastructure
- Under-construction projects within 3 km (verified)0Reliable
- Earlier-stage projects within 3 km (sanctioned/tendered/observed)3Caveat
ReliableFrom our location report at the builder-entered pin (12.88613, 77.70380), 2026-10-24. Each figure's source and caveat are in the full report.