Neighborhood IntelOpen on the map

RERA project · Residential/Group Housing

63 degree east - Tower B

by APG Intelli Homes Private Limited · 325 homes · 2.26 acres · 1 tower · Bengaluru East

Past due, no completion filed Past its deadline of 30 Jun 2023, and no completion is filed on RERA. Some finished projects never file, so ask the builder for the occupancy certificate.

Location report

At a glance

Is it on schedule?Past due
Past its deadline

The deadline was 30 Jun 2023, and no completion is filed.

How much is sold?Unknown
Not reported

The builder has not filed bookings on RERA.

How crowded is it?More crowded
144 homes per acre

Similar projects across the city: 76 per acre. 32% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project. 4 more about the builder's other projects.

Any legal cases?Unknown
Not stated

The RERA page doesn't say.

What is the builder's record?28 due so far
25% on time

Of its 54 RERA projects in Bengaluru Urban: 7 delivered on time, 11 late (after the date first promised), 10 past due with no completion filed, 26 under way.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 May 2019
  2. Approved by RERA4 May 2019
  3. First promised30 Sep 2022

    The date the builder gave at registration.

  4. Deadline (extended)30 Jun 2023

    Passed with no completion filed.

No quarterly construction update is filed on this project's RERA page.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

What's being built?

3BHK
  • 972 sq ft144 homes90.3 m²
  • 955 sq ft24 homes88.7 m²
Typically 51 m² land share · 8 m² balcony/terrace · 1 parking space
168 homes · 52% of the project
2BHK
  • 793 sq ft104 homes73.7 m²
  • 864 sq ft12 homes80.3 m²
  • 847 sq ft2 homes78.7 m²
Typically 42 m² land share · 8 m² balcony/terrace · 1 parking space
118 homes · 36% of the project
STUDIO
  • 346 sq ft26 homes32.1 m²
  • 321 sq ft13 homes29.8 m²
Typically 17 m² land share · 1 parking space
39 homes · 12% of the project

Carpet areas from the builder's flat-by-flat list on RERA, each size as listed with how many homes have it. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

Tower-B14 floors

Tower-B: 325 homes

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project144
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project32%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.26 acres

9,147 m²

Ground covered by buildings
68% of the land

6,223 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

All 54 RERA projects of Assetz on the map

Complaints to RERA about its other projects

The company

Registered as
APG Intelli Homes Private Limited
Type
Company
Company number
U70100KA2014PTC077189

CIN or LLPIN, from the Registrar of Companies.

PAN
AANCA0060C

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land
₹25.8 cr
Construction
₹173.2 cr
Total project cost
₹199.0 cr

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

This project lists no location on RERA, so there is no location report for it.