RERA project · Residential/Group Housing

4SQUARE PARK SIERRA

by 4SQUARE ESTATES · 170 homes · 2.90 acres · 1 tower · Yelahanka

Upcoming Under construction, due Dec 2029. 29% built with 16% of the time used. 8% of homes booked.

Location report

At a glance

Is it on schedule?Never extended
29% built

Due 31 Dec 2029. 16% of the time from RERA approval to the deadline has passed.

Built29%
Time used16%
How much is sold?156 left
8% booked

14 of 170 homes, as the builder reported for Q2 2026-27.

How crowded is it?Less crowded
59 homes per acre

Similar projects within 3 km: 74 per acre. 65% of the land is left open.

Any complaints?None filed
None

Complaints to RERA about this project.

Any legal cases?None declared
None declared

No litigation on the land or the project, as the builder declares it to RERA.

What is the builder's record?No other record
Only this project

It is the only RERA project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

These answers come from the builder's own filings on RERA Karnataka and RERA's records. They are not checked on site; each section below shows the detail.

When will it be ready?

  1. Work started1 Jan 2026
  2. Approved by RERA17 Mar 2026
  3. Today24 Oct 2026

    16% of the time to the deadline has passed.

  4. If it slips like a typical project2 Oct 2030

    35% of 4,105 active projects in Bengaluru Urban have extended their deadline, by a median of 275 days.

How much is built, each quarter

Q4 2025-265%
Q1 2026-2712%
Q2 2026-2729%

Built, as the builder reports itTime used by then

When the bar is short of the mark, construction is behind a steady pace. Builders rarely work at a steady pace, so read it as a rough guide.

CaveatDates from the RERA Karnataka project list, 24 Oct 2026. Progress as the builder reports it each quarter, certified by its architect and engineer; not checked on site.

How much is sold?

14 booked156 leftQ2 2026-27

Still available: 5 × 2 BHK, 19 × 2.5 BHK, 132 × 3 BHK.

Booked, by type

2 BHK0 of 5
2.5 BHK1 of 20
3 BHK13 of 145

Booked, each quarter

Q4 2025-262 of 170
Q1 2026-276 of 170
Q2 2026-2714 of 170

Booked means sold or reserved, as the builder reports it. It says nothing about prices.

CaveatFrom the builder's quarterly updates to RERA Karnataka.

What's being built?

3 BHK
1,202 sq ft
112 m² carpet · sizes 787–1,251 sq ft (12 at this size)
72 m² land share · 18 m² balcony/terrace · 1 parking space
145 homes · 85% of the project
2.5 BHK
1,075 sq ft
100 m² carpet · sizes 818–1,234 sq ft (5 at this size)
57 m² land share · 14 m² balcony/terrace · 1 parking space
20 homes · 12% of the project
2 BHK
1,142 sq ft
106 m² carpet · sizes 1,056–1,142 sq ft (4 at this size)
56 m² land share · 19 m² balcony/terrace · 1 parking space
5 homes · 3% of the project

Sizes from the builder's flat-by-flat list on RERA: the size most homes of each type have, and the range. Carpet area is the floor area inside the walls of a home, the figure RERA requires builders to sell by. Land share (the undivided share) is the part of the land that comes with each home.

Towers

4Square Park Sierra6 floors

4Square Park Sierra: 170 homes, 15 m tall, 1 basement

Amenities

CaveatAs registered by the builder on RERA Karnataka.

How crowded is it?

Homes per acre

This project59
Typical within 3 km (73)74
Typical in the city (3,044)76

Fewer homes on each acre usually means less crowding: less traffic, quieter common areas.

Land left open

This project65%
Typical within 3 km (75)54%
Typical in the city (3,151)56%

The share of the land not built on, which includes roads.

Land
2.90 acres

11,736 m²

Ground covered by buildings
35% of the land

4,119 m²

Floor-area ratio
20527.90

Floors built per unit of land: 20527.90 m² of floors for each m² of land.

Parking
1.12 per home

190 covered, 0 open

Built-up area, all floors
2,88,957 sq ft

26,845 m²

CaveatAs registered on RERA Karnataka. "Typical" is the median of active residential/group housing projects with a land area on RERA; the comparison is ours.

Who is building it?

This is the only project registered under this company name in Bengaluru Urban. Builders often register projects under other companies.

The company

Registered as
4SQUARE ESTATES
Type
Partnership Firm
PAN
AADFZ6494Q
GSTIN
29AADFZ6494Q1ZX

The land is owned together with others (a joint development).

CaveatFrom the builder's own filings on this project's RERA page; complaints from RERA's list.

Project cost

Land ₹42.7 crBuilding and development ₹101.1 crTotal ₹145.7 cr
Money from buyers, each quarter
QuarterCollected from buyersWithdrawn from the project account
Q4 2025-26₹43.0 lakh₹0.0 lakh
Q1 2026-27₹1.1 cr₹74.1 lakh
Q2 2026-27₹1.8 cr₹1.6 cr

Builders fill these in differently: some give the quarter, some the total so far, and the totals don't always add up. Read them as rough.

CaveatCost as certified by the builder's chartered accountant at registration.

What's around it?

Open the full location report on the map

Metro, rail, bus, airport

  • Nearest operational metro station9.83 kmReliable
  • Nearest railway station1.58 kmReliable
  • Bus stops within 500 m2Caveat

Parks, shops, daily needs

  • Supermarkets within 1 km3Caveat
  • Parks within 1 km2Caveat
  • Nearest lake / water body (≥2 ha)1.11 kmCaveat

Hospitals

  • Nearest hospital0.43 kmCaveat

Schools

  • Schools in pincode 560064 (UDISE+ census)240Caveat
  • Private (classes 1–10 or 1–12), government and central schools within 1 km5Caveat
  • Median pupil-teacher ratio, schools within 1 km26.8 :1Caveat
  • Schools with library + playground + ICT lab (1 km)3Caveat

Police and crime

  • Reported IPC/BNS crimes, Bengaluru City (2025)37,181 casesCaveat
  • Police station jurisdictionYelahanka PSReliable

Flood and waterlogging

  • BBMP-listed flood / low-lying spots within 1 km2Caveat

Water availability

  • Groundwater stage (CGWB block assessment)Over ExploitedCaveat
  • Groundwater depth at nearest CGWB well16.2 m below groundCaveat
  • In an IISc groundwater-critical ward (2025 outlook)yesCaveat

Power reliability

  • Avg outage minutes per feeder, city circles (2026-08)18.9 min/monthCaveat
  • Un/partially-electrified layouts within 1 km4Caveat

Landfills, sewage plants, industry, aircraft

  • Nearest named landfill / dump site (≥2 ha)4.82 kmReliable
  • Nearest sewage treatment plant0.39 kmCaveat
  • Industrial zones within 1 km1Caveat
  • Nearest airfield runway (any, incl. military)1.99 kmCaveat
  • Nearest commercial-airport runway14.07 kmReliable
  • Distance to runway approach-path proxy9.09 kmCaveat

Upcoming infrastructure

  • Under-construction projects within 3 km (verified)1Reliable
  • Earlier-stage projects within 3 km (sanctioned/tendered/observed)4Caveat

ReliableFrom our location report at the builder-entered pin (13.09551, 77.60274), 2026-10-24. Each figure's source and caveat are in the full report.